All Exams Test series for 1 year @ ₹349 only
Question

When NPV and IRR give different rankings, which of the following problem is the cause of disparity that arises when the initial investment in mutually exclusive projects is different ?

The correct answer is
Size-Disparity Problem

Understanding NPV vs IRR Ranking Disparities

Net Present Value (NPV) and Internal Rate of Return (IRR) are crucial metrics used in finance to evaluate the potential profitability of investment projects. Both methods help decision-makers choose between different investment opportunities. However, they can sometimes produce conflicting rankings, particularly when evaluating mutually exclusive projects.

  • NPV (Net Present Value): This calculation determines the present value of all expected future cash flows generated by a project, minus the initial investment cost. It measures the absolute increase in wealth a project is expected to generate.
  • IRR (Internal Rate of Return): This is the discount rate at which the NPV of a project's cash flows equals zero. It represents the project's percentage rate of return.

Common Reasons for NPV and IRR Conflicts

Conflicts between NPV and IRR rankings typically arise under specific circumstances:

  • Different Initial Investment Sizes: Projects requiring significantly different initial outlays.
  • Different Timing of Cash Flows: Projects where the bulk of cash flows occur at different times.
  • Unequal Project Lives: Projects having different durations or operational lifespans.

Identifying the Size-Disparity Problem

The question specifically highlights the situation where the disparity between NPV and IRR rankings occurs due to differences in the initial investment for mutually exclusive projects. This specific issue is known as the Size-Disparity Problem.

The Size-Disparity Problem arises because:

  • NPV provides a measure of absolute profitability. A larger initial investment, even with a lower IRR, might generate a higher absolute cash inflow in present value terms, thus resulting in a higher NPV.
  • IRR focuses on the rate of return. A smaller initial investment might yield a higher IRR, indicating greater percentage efficiency, but the overall value added (NPV) might be less than that of a larger-scale project.

For example, Project A might require a $1 million investment and yield an IRR of 20% with an NPV of $500,000. Project B might require a $100,000 investment and yield an IRR of 30% with an NPV of $200,000. While Project B has a higher IRR, Project A is generally preferred if they are mutually exclusive because it adds more absolute value ($500,000 > $200,000) to the firm.

Resolving Ranking Conflicts

When comparing mutually exclusive projects, the NPV rule is generally considered the theoretically superior method because it directly addresses the goal of maximizing firm value. The Size-Disparity Problem underscores why relying solely on IRR can be misleading when initial investments differ.

Therefore, the cause of disparity specifically linked to different initial investments is the Size-Disparity Problem.

Was this answer helpful?

Important Questions from Capital budgeting decisions

  1. Zero Based Budgeting (ZBB) lays emphasis on:

    A. Allocation of resources based on cost-benefit terms

    B. Unlimited deficit financing

    C. Preparing a new budget right from the scratch

    D. Preparing the budget, neglecting the history of expenditure

    Choose the correct answer from the options given below:

  2. Indicate the correct code for discounted cash flow techniques for capital investment proposals from the following:

    (i) Net Present Value Method

    (ii) Internal Rate of Return method

    (iii) Excess Benefit-Cost Ratio method

    (iv) Net Terminal Value method

    Choose the correct answer from the code given below :

  3. Break even analysis is also known as:

  4. Match List - I with List - II :

    List - I (Methods)List - II (Description)
    A. Net present valueI. Ratio of PV of inflows to investment
    B. Internal rate of returnII. Rate where NPV = 0
    C. Profitability indexIII. Present value of inflows – Present value of outflow
    D. Payback periodIV. Time to recover initial cost

    Choose the correct answer from the options given below :

  5. Arrange the process of capital budgeting in proper sequence.
    A. Identification of potential investment opportunities
    B. Decision making
    C. Assembling of proposed investments
    D. Preparation of capital budget and appropriation
    E. Implementation
    Choose the correct answer from the options given below :
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App