What is the correct sequence of the temporary adjustment of level?

The correct answer is
Setting, centering and leveling

Level Instrument Temporary Adjustment Sequence

Temporary adjustments are crucial steps performed whenever a level instrument is set up at a new location to ensure accurate measurements. These adjustments must be done in a specific order.

Key Adjustment Steps

The sequence involves preparing the instrument for sighting:

  1. Setting:
    • First, place the tripod over the station point where the instrument will be used.
    • Mount the level instrument securely on the tripod head.
    • Adjust the tripod legs to position the instrument approximately over the station point.
  2. Centering:
    • Accurately position the instrument directly above the station mark.
    • This step ensures the instrument is precisely located over the point of measurement.
  3. Leveling:
    • Use the instrument's leveling screws to move the bubble in the plate level vial until it is exactly centered between its extreme positions.
    • This action makes the instrument's horizontal plane truly horizontal, ensuring the line of sight is level.

Following this order, Setting, Centering, and Leveling, allows for precise surveying measurements.

Was this answer helpful?

Important Questions from Fundamental Concepts

  1. Mean Sea Level for India is :

  2. Which of the following quantities are each equal to one acre?

    A. 43560 sq ft

    B. 40 gunthas

    C. 10 sq gunter's chain

    D. 4850 sq yds

    Choose the correct answer below.

  3. The capacity of a telescope of producing a sharp image is called it

  4. The error due to bad ranging is:

  5. 1 Nautical mile equals to how many metres?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App