Question

The stage of plate laying in track construction includes:

The correct answer is

placing of rail and sleepers

Understanding Plate Laying in Track Construction

Railway track construction is a multi-stage process that involves preparing the ground and assembling the track structure. One crucial stage in this process is known as plate laying or track laying.

The question asks about the specific activities included in the stage of plate laying in track construction. Let's examine the options provided:

  • Option 1: placing of fish plates - Fish plates are used to connect two adjacent rails. While essential for a continuous track, placing fish plates is typically done as part of assembling the rail lengths *after* the rails themselves have been positioned on the sleepers during the initial laying process.
  • Option 2: placing of rail and sleepers - This involves bringing the main components of the track – the rails and the sleepers (which support the rails) – and positioning them onto the prepared subgrade or ballast bed. This action directly constitutes the act of "laying" the track structure.
  • Option 3: preparation of formation - The formation is the prepared ground or subgrade upon which the track structure rests. Preparation of the formation, which includes excavation, filling, and compaction, is a fundamental step that occurs *before* the plate laying stage begins.
  • Option 4: placing of rails, sleepers and ballast - Ballast (crushed stone or gravel) is a layer placed beneath and around the sleepers. While some initial ballast might be spread before placing sleepers, the main ballasting operation, including packing and consolidating the ballast around the sleepers, is done *after* the rails and sleepers are laid and the track is aligned.

Based on the typical sequence of railway track construction, the stage of plate laying primarily involves placing the principal track components: the rails and the sleepers, onto the prepared formation or initial ballast layer. Subsequent activities like connecting rails with fish plates, full ballasting, tamping, and alignment follow this initial laying.

Therefore, the most accurate description of the plate laying stage among the given options is the placing of rail and sleepers.

Stages of Track Construction (Simplified Sequence)

  1. Land acquisition and clearing
  2. Formation preparation (subgrade)
  3. Initial ballast spreading (sometimes)
  4. Plate Laying (Placing of sleepers and rails)
  5. Joining of rails (using fish plates or welding)
  6. Ballasting and tamping
  7. Track alignment and levelling
  8. Final surfacing and inspection

As highlighted above, plate laying fits specifically into the sequence as the placement of rails and sleepers.

Analysis of Options in relation to Plate Laying

Activity Relation to Plate Laying Stage
Placing of fish plates Usually done after rails are placed on sleepers, to join them.
Placing of rail and sleepers This is the core activity of the plate laying stage.
Preparation of formation Done before the plate laying stage.
Placing of rails, sleepers and ballast Ballasting is mainly done after rails and sleepers are laid and roughly aligned.

The process of plate laying is fundamental to establishing the railway line, providing the base structure for trains to run on. It requires careful planning and execution to ensure the correct gauge and alignment are maintained during the placement of sleepers and rails.

Revision Table: Key Stages of Track Construction

Stage Description
Formation Preparation Preparing the ground base for the track.
Plate Laying Placing sleepers and rails on the prepared formation/initial ballast.
Ballasting & Tamping Adding ballast, compacting it around sleepers for support and drainage.
Alignment & Levelling Adjusting the track position and height to meet specifications.

Additional Information on Railway Track Components

Understanding the different components helps in understanding the stages of track construction like plate laying.

  • Rails: Steel sections that provide the running surface and guidance for train wheels. They are laid longitudinally.
  • Sleepers: Also called ties (especially in North America). These are transverse supports (made of wood, concrete, or steel) that hold the rails at the correct gauge and transfer the load from the rails to the ballast.
  • Ballast: A layer of crushed rock or gravel beneath and around the sleepers. It provides support, drainage, lateral stability, and allows for track adjustments.
  • Fastenings: Devices that connect the rails to the sleepers (e.g., spikes, clips, bolts).
  • Fish Plates: Steel plates bolted to the ends of two rails to connect them mechanically and electrically.
  • Formation: The earthwork subgrade upon which the ballast and track structure are laid. It must be stable and well-compacted.

The plate laying stage focuses on bringing the rails and sleepers together onto the prepared formation, setting the stage for the track to be fully assembled and made operational.

Was this answer helpful?

Important Questions from Miscellaneous

  1. A stone is thrown horizontally from the top of a 20 m high building with a speed of 12 m/s. It hits the ground at a distance R from the building. Taking g = 10 m/s2 and neglecting air resistance will give :

  2. A mass is attached to a spring that hangs vertically. The extension produced in the spring is 6 cm on Earth. The acceleration due to gravity on the surface of the Moon is one-sixth of its value on the surface of the Earth. The extension of the spring on the Moon would be:

  3. Directions: Each item in this section consists of a sentence with an underlined word followed by four words (a), (b), (c), and (d). Select the option that is opposite in meaning to the underlined word and mark your response in your Answer Sheet accordingly.

    The deluge affected the population.
  4. The major source of vitamins and minerals for vegetarians is

  5. Which of the following statements about the Deccan Riots Commission is/are correct?

    1. The Commission did not hold enquiries in the districts which were not affected.

    2. The Commission did record the statements of ryots, sahukars and eye-witnesses.

    Select the correct answer using the code given below:

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App