The second stage of survey to examine the general character of the area for deciding the most feasible routes is known as-
Reconnaissance
Planning and constructing a new route, such as a road, railway, or pipeline, involves several stages of surveying. These stages are conducted sequentially to identify the most suitable path considering factors like topography, soil conditions, land use, environmental impact, and cost.
While terminology and the exact number of stages can vary slightly, a common breakdown includes the following:
The question asks about the second stage of the survey that examines the general character of the area for deciding the most feasible routes. Based on the common sequence described above where an initial study precedes the field work, the second stage is the Reconnaissance Survey.
During the Reconnaissance Survey, surveyors walk or drive along potential routes, observing the landscape, slopes, curves required, necessary cuts and fills, soil types, rock outcrops, and drainage conditions. The objective is to assess the practical feasibility of the routes and identify major obstacles or challenges without using precise instruments for detailed measurements. This general examination helps in making informed decisions about which routes to pursue in the more costly preliminary survey stage.
| Stage Number | Name of Stage | Key Activities | Purpose |
|---|---|---|---|
| 1 | Initial Study / Desk Study | Review maps, reports, imagery | Gather existing data, identify potential corridors |
| 2 | Reconnaissance Survey | Field inspection, visual assessment | Examine general character, assess feasibility, identify promising routes |
| 3 | Preliminary Survey | Detailed topographic survey, running traverses | Collect precise data for maps & profiles, analyze alternative routes |
| 4 | Final Location Survey | Staking out centerline, detailed cross-sections | Provide data for construction of the chosen route |
Considering this sequence, the Reconnaissance Survey fits the description provided in the question as the second stage focused on examining the general character to decide on feasible routes.
| Survey Stage | Primary Goal | Methodology |
|---|---|---|
| Initial Study | Preliminary corridor identification | Desk research, map analysis |
| Reconnaissance | Assess general ground feasibility | Field observation, visual assessment |
| Preliminary | Detailed data collection on options | Instrumental surveying, mapping |
| Final Location | Precise route staking for construction | High-precision instrumental surveying |
The process of route location is crucial for infrastructure projects. Choosing the optimal route minimizes construction costs, reduces environmental impact, ensures safety, and maximizes the usability of the final structure. Several factors influence route selection:
Effective route surveying through these stages ensures that all these factors are considered systematically to arrive at the best possible route for the intended purpose.
For an IRC Class AA loading train, the nose-to-tail spacing between successive tracked vehicles shall not be less than ________.
The maximum scour depth dim for the condition of flow at noses of piers is
The sequence of four stages of the survey in a highway alignment is _________
The "Swachh Bharat Abhiyan" was launched by the Government of India in which year?
Which of these methods of tunnel construction is not suitable in rocks?