Question

The rate of construction of a hospital is expressed in terms of cost per head. This type of Estimate is called as _______

The correct answer is

Functional unit estimate

Based on this analysis, the method that expresses the rate of construction for a hospital in terms of "cost per head" (which represents the functional capacity) is the Functional Unit Estimate. The estimate type where the rate of construction is expressed based on the functional capacity, such as cost per bed or cost per head for a hospital, is known as a Functional Unit Estimate.

Was this answer helpful?

Important Questions from Measurement

  1. Which of the following is the unit of measurement for the sills of windows?

  2. What percentage of the cost of the estimate is provided for the work charged establishment?

  3. What is the thickness (inches) of the one brick wall made up of traditional brick?

  4. Which one is the CORRECT option for the damp proof course?

  5. What is the density of the mild steel in quintal per cubic meter?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App