Question

The process of marking the positions of various foundations and other elements on to the ground as per the drawings is called as

The correct answer is

Setting out of foundations

Understanding Foundation Marking: Setting Out

The question asks about the specific term used in construction and civil engineering for marking the exact positions of various foundations and other structural elements directly onto the ground according to the architectural and structural drawings. This is a crucial initial step in any construction project.

What is Setting Out of Foundations?

The process described in the question is known as "Setting out of foundations" or more generally, "Setting out" or "Layout." It involves transferring the details from the building plans, such as the location, dimensions, and alignment of foundation walls, columns, and footings, onto the construction site itself. This is typically done using measuring tapes, strings, pegs, chalk lines, and surveying instruments like total stations or theodolites to ensure accuracy.

Think of it as drawing the plan on the ground so that the construction team knows exactly where to dig for the foundations and where to build the walls and columns.

Analyzing the Options:

Let's look at why the other options are not correct terms for this specific process:

  • Settlement of foundations: This refers to the downward movement or sinking of a structure and its foundation into the soil over time due to the load applied. This happens *after* the foundation is constructed and the building is erected, not during the initial marking phase.
  • Settling of foundations: Similar to settlement, this term also describes the process of the foundation coming to rest or sinking. It is related to post-construction behavior, not the initial layout process.
  • Siting of foundations: This refers to the process of choosing the appropriate location or site for the entire structure, taking into consideration factors like soil conditions, topography, accessibility, and planning regulations. While important before setting out, it is not the act of marking positions on the ground.
  • Setting out of foundations: As discussed, this term correctly describes the process of accurately marking the positions and dimensions of foundations and other structural elements on the ground based on the construction drawings.

Based on standard construction terminology, "Setting out of foundations" is the accurate term for transferring the foundation plan onto the ground.

Term Meaning Relation to Construction Phase
Settlement of foundations Downward movement/sinking of foundation post-construction Post-construction behavior
Settling of foundations Coming to rest/sinking of foundation Post-construction behavior
Siting of foundations Choosing the location/site for the structure Planning/Design phase (before marking)
Setting out of foundations Marking foundation positions and dimensions on the ground Initial site work/Construction phase

Therefore, the process of marking the positions of various foundations and other elements onto the ground as per the drawings is accurately called Setting out of foundations.

Revision Table: Foundation Terminology

Term Key Action/Description
Setting Out Transferring drawing layout to the ground using marks, pegs, lines.
Foundation The part of a structure that transmits loads from the building to the ground.
Settlement Downward movement of foundation/structure after construction.

Additional Information: Importance of Accurate Setting Out

Accurate setting out is critical for the entire construction project. Errors during setting out can lead to:

  • Incorrect positioning of foundations, walls, and columns.
  • Misaligned structural elements.
  • Problems with connecting different parts of the building.
  • Issues with property boundaries.
  • Increased costs due to rework.

Surveyors and engineers use precise tools and techniques, including coordinate systems, to ensure the layout on the ground exactly matches the design drawings. This includes establishing benchmarks ( fixed reference points) on site.

Was this answer helpful?

Important Questions from Substructure

  1. The portions of the structure below the ground level are called as

  2. A layer provided to prevent entry of unwanted moisture inside the building either by seepage or by leakage is known as

  3. The structure which is used to divide the stages in different levels is termed as-

  4. Temporary arrangement of boardings, wailings and struts which is provided to give support to sides of trench is known as___________.

  5. Under which of the following types of the dampness-checking materials categories, does cement concrete fall?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App