The process of marking the positions of various foundations and other elements on to the ground as per the drawings is called as
Setting out of foundations
The process described in the question is known as "Setting out of foundations" or more generally, "Setting out" or "Layout." It involves transferring the details from the building plans, such as the location, dimensions, and alignment of foundation walls, columns, and footings, onto the construction site itself.
Temporary arrangement of boardings, wailings and struts which is provided to give support to sides of trench is known as___________.
The portions of the structure below the ground level are called as
A layer provided to prevent entry of unwanted moisture inside the building either by seepage or by leakage is known as
The structure which is used to divide the stages in different levels is termed as-
The layout for substructure work must consider nearby underground based utilities because: