The normal duration and normal cost of activity are 24 days and Rs. 50,000 respectively. The activity crash duration is 22 days and the indirect cost is Rs1000 per day. If the cost slope is Rs. 1500 per day, then the total cost of activity after the crashing will be:
Rs. 51,000
In project management, crashing an activity means reducing its duration below the normal duration to potentially shorten the overall project length. This is often done at an increased cost, known as the crash cost. The cost slope represents the additional direct cost incurred for each unit of time the activity duration is reduced.
The total cost of an activity includes both direct cost and indirect cost. Crashing typically increases the direct cost but reduces the indirect cost (because the duration is shorter). The goal is often to find the duration that minimizes the total cost.
Let's break down the calculation based on the information provided:
First, let's determine the indirect cost at the normal duration.
Indirect Cost at Normal Duration = $T_{normal}$ × Indirect Cost per day
Indirect Cost at Normal Duration = 24 days × Rs. 1000/day = Rs. 24,000
Assuming the given Normal Cost (Rs. 50,000) is the Total Cost at normal duration, we can find the Normal Direct Cost.
Normal Direct Cost = Normal Total Cost - Indirect Cost at Normal Duration
Normal Direct Cost = Rs. 50,000 - Rs. 24,000 = Rs. 26,000
Now, let's calculate the reduction in duration due to crashing.
Duration Reduction = $T_{normal}$ - $T_{crash}$
Duration Reduction = 24 days - 22 days = 2 days
The cost slope tells us how much the direct cost increases for each day of reduction. Let's calculate the increase in direct cost due to crashing.
Increase in Direct Cost = Duration Reduction × Cost Slope
Increase in Direct Cost = 2 days × Rs. 1500/day = Rs. 3000
Now we can find the direct cost of the activity after crashing.
Direct Cost After Crashing = Normal Direct Cost + Increase in Direct Cost
Direct Cost After Crashing = Rs. 26,000 + Rs. 3000 = Rs. 29,000
Next, we calculate the indirect cost at the crashed duration.
Indirect Cost After Crashing = $T_{crash}$ × Indirect Cost per day
Indirect Cost After Crashing = 22 days × Rs. 1000/day = Rs. 22,000
Finally, the total cost of the activity after crashing is the sum of the direct cost after crashing and the indirect cost after crashing.
Total Cost After Crashing = Direct Cost After Crashing + Indirect Cost After Crashing
Total Cost After Crashing = Rs. 29,000 + Rs. 22,000 = Rs. 51,000
Therefore, the total cost of the activity after crashing will be Rs. 51,000.
Which one of the following distributions provides information regarding the uncertainty of duration time estimates is PERT described network?
Which of the following distribution represents the time estimates in PERT ?
Negative slack occurs when -
In PERT analysis, the possible number of time estimates for activities linking up two events are -
The amount of time by which an activity can be delayed without affecting project completion time is