Plane tabling
In the field of surveying, different methods are employed to measure and map the features of the Earth's surface. Each method has specific characteristics and applications. The question asks for the method where field work and plotting work are done simultaneously.
Plane tabling is a graphical method of surveying in which the field work and plotting work are carried out concurrently. This means that the surveyor observes the details in the field and immediately draws them on the drawing sheet mounted on the plane table. This unique characteristic makes it distinct from other surveying methods where field observations are first recorded in a field book and then plotted in the office.
To better understand why plane tabling is the answer, let's briefly look at the other surveying methods mentioned in the options:
Compass surveying involves determining the direction of survey lines using a magnetic compass and measuring distances using a chain or tape.
Chain surveying is the simplest method of surveying, where only linear measurements are taken in the field. It is suitable for small areas with simple details and flat terrain.
Levelling is a surveying technique used to determine the relative heights or elevations of different points on or below the surface of the Earth.
| Surveying Method | Field Work & Plotting Relationship | Primary Output |
|---|---|---|
| Plane Tabling | Simultaneous (plotting done directly in field) | Map, Plan |
| Compass Surveying | Sequential (field notes taken, then plotted in office) | Traverse lines, Plan |
| Chain Surveying | Sequential (measurements taken, then plotted in office) | Plan (based on linear measurements) |
| Levelling | Sequential (readings taken, then calculations/drawings in office) | Elevations, Profiles, Contour maps |
Based on the analysis, plane tabling is the only surveying method among the given options where the field work and plotting work are carried out simultaneously. This efficiency and the ability to detect errors on site are its key advantages.
The objective of two-point problem which is solved with the resection method is:
Three point problem can be solved by
Which of the following is NOT a type of error in Plane Table Surveying?
The first temporary adjustment to be done after setting up the plane table at any station will be
In solving three point problem by trial and error process, the fix strength is good when: