The following statements (C1, C2, C3, C4) pertain to the characteristics of different type of canals. Which of the following statements is/are correct? C1: A contour canal can irrigate command areas on both the banks. C2: It is possible to construct a contour canal with banks on one side only. C3: In the case of a ridge canal, the number of cross drainage works are maximum. C4: Side slope canal is aligned roughly at right angles to the ground contours.
C2 and C4 only
Canals are artificial channels built to convey water, primarily for irrigation, but also for navigation, drainage, or hydropower generation. Their alignment and construction depend heavily on the topography of the region they traverse. Different types of canals are designed to suit varying ground conditions, leading to distinct characteristics regarding irrigation area, banking requirements, and the number of cross drainage works needed.
Let's analyze the characteristics of the canal types mentioned in the statements: Contour canals, Ridge canals, and Side slope canals.
A contour canal is constructed roughly parallel to the contours of the area. This type of canal is typically aligned on a sloping ground. Key characteristics include:
A ridge canal, also known as a watershed canal, is aligned along the watershed line or ridge line of the area. This is the highest elevation line from which water flows down on either side. Characteristics include:
A side slope canal is constructed on a side slope, essentially running perpendicular or nearly perpendicular to the contour lines, across the slope. Characteristics include:
Let's examine each statement based on the characteristics discussed:
C1: A contour canal can irrigate command areas on both the banks.
This statement is incorrect. A contour canal runs parallel to contours on sloping ground. Water can easily flow downhill from the canal to irrigate the area on the lower side. Irrigating the area on the uphill side is generally not possible or requires lifting the water, which is not a typical characteristic of basic contour canal irrigation.
C2: It is possible to construct a contour canal with banks on one side only.
This statement is correct. Due to the alignment along a slope, a contour canal will often have cutting on the uphill side and filling on the downhill side. The bank is primarily needed on the downhill side (the 'fill' side) to retain the water level. The uphill side may require less or no banking depending on the extent of cutting into the natural ground.
C3: In the case of a ridge canal, the number of cross drainage works are maximum.
This statement is incorrect. A ridge canal follows the watershed line, which is the highest elevation. Natural drainage lines flow away from the ridge. Therefore, a ridge canal runs between the drainage paths, minimizing the need for cross drainage structures. The number of cross drainage works is typically minimum for a ridge canal, not maximum.
C4: Side slope canal is aligned roughly at right angles to the ground contours.
This statement is correct. A side slope canal is built on a steep slope and is designed to carry water down or across that slope. This alignment is typically perpendicular or at a significant angle (roughly at right angles) to the contour lines, which represent lines of equal elevation.
Based on the analysis, statements C2 and C4 are correct, while C1 and C3 are incorrect.
Therefore, the correct statements are C2 and C4 only.
| Feature | Contour Canal | Ridge Canal | Side Slope Canal |
|---|---|---|---|
| Alignment relative to Contours | Parallel | Along Ridge/Watershed | Roughly perpendicular |
| Irrigation Area | One side (lower) | Both sides | Limited, often for specific areas downhill |
| Cross Drainage Works | Significant number | Minimum number | Relatively few major ones, but may need to manage minor hill drains |
| Banking | Often on one side (lower) | Usually on both sides | Significant cutting/filling, specific banking depends on design |
Cross drainage works are structures built to carry a canal over or under a natural drain (like a river, stream, or nala). Their type depends on the relative levels of the canal bed and the drain bed, and whether the drain is perennial or seasonal.
The choice of canal alignment significantly impacts the number and type of these structures, affecting the overall cost and complexity of the irrigation project.
Upon a detailed topographical investigation, an engineer wants to align a canal. Along which of the following should be align the canal?
Which of the following components of the weir divides the river width into weir portion and under sluices pocket?
Which canal irrigates only on one side because the area on the other side is higher?
In which type of canal escapes is the crest of the weir wall kept at R.L. equal to the canal FSL?
If the discharge in canal equals to 70 m3/s with it silt factor √2, the velocity of flow in canal as per Lacey’s theory is