All Exams Test series for 1 year @ ₹349 only
Question

The completion of a construction job may be delayed due to strike. The probability of strike is 0.6. The probability that the construction job gets completed on time if there is no strike is 0.85 and the probability that the construction job gets completed on time if there is a strike is 0.35. What is the probability that the construction job will not be completed on time ?

The correct answer is

0.45

Calculating the Probability of Construction Job Delay

The question asks for the probability that a construction job will not be completed on time. We are given probabilities related to a strike and the impact of a strike (or no strike) on the job completion time.

Let's define the events:

  • \(S\): The event that there is a strike.
  • \(S^c\): The event that there is no strike.
  • \(C\): The event that the construction job is completed on time.
  • \(C^c\): The event that the construction job is not completed on time.

We are given the following probabilities:

  • Probability of strike, \(P(S) = 0.6\).
  • Probability of no strike, \(P(S^c)\). Since having a strike or not having a strike are complementary events, \(P(S^c) = 1 - P(S) = 1 - 0.6 = 0.4\).
  • Probability of completion on time given no strike, \(P(C | S^c) = 0.85\). This is a conditional probability.
  • Probability of completion on time given strike, \(P(C | S) = 0.35\). This is also a conditional probability.

We need to find the probability that the construction job will not be completed on time, which is \(P(C^c)\).

We can find \(P(C^c)\) by first finding the probability that the construction job is completed on time, \(P(C)\), and then using the fact that \(C\) and \(C^c\) are complementary events:

\(P(C^c) = 1 - P(C)\)

Applying the Law of Total Probability

The events \(S\) (strike) and \(S^c\) (no strike) are mutually exclusive (they cannot happen at the same time) and exhaustive (one of them must happen). In such cases, we can use the Law of Total Probability to find the probability of an event \(C\) that depends on these events:

\[P(C) = P(C | S) \cdot P(S) + P(C | S^c) \cdot P(S^c)\]

Let's plug in the given values:

  • \(P(S) = 0.6\)
  • \(P(S^c) = 0.4\)
  • \(P(C | S) = 0.35\)
  • \(P(C | S^c) = 0.85\)

Now, calculate \(P(C)\):

\[P(C) = (0.35 \times 0.6) + (0.85 \times 0.4)\] \[P(C) = 0.21 + 0.34\] \[P(C) = 0.55\]

So, the probability that the construction job is completed on time is 0.55.

Calculating the Probability of Not Completing on Time

We want to find \(P(C^c)\), the probability that the construction job will not be completed on time. Since \(C\) and \(C^c\) are complementary events, their probabilities sum to 1:

\[P(C^c) = 1 - P(C)\]

Using the value of \(P(C) = 0.55\):

\[P(C^c) = 1 - 0.55\] \[P(C^c) = 0.45\]

Therefore, the probability that the construction job will not be completed on time is 0.45.

Revision Table: Construction Job Probability

Event Probability Description
Strike (S) 0.6 Probability of a strike occurring.
No Strike (Sc) 0.4 Probability of no strike occurring.
Completion on time | Strike (C | S) 0.35 Probability of completing on time given a strike happens.
Completion on time | No Strike (C | Sc) 0.85 Probability of completing on time given no strike happens.
Completion on time (C) 0.55 Calculated probability of completing the job on time.
Not Completion on time (Cc) 0.45 Calculated probability of not completing the job on time.

Additional Information: Probability Concepts

This problem utilizes several fundamental concepts in probability:

  • Conditional Probability: The probability of an event occurring given that another event has already occurred. \(P(A|B)\) is the probability of event A happening given event B has happened.
  • Mutually Exclusive Events: Events that cannot occur at the same time. In this problem, 'strike' and 'no strike' are mutually exclusive.
  • Exhaustive Events: A set of events is exhaustive if at least one of the events must occur. 'Strike' and 'no strike' are exhaustive because either there is a strike or there isn't.
  • Law of Total Probability: This rule is used to find the total probability of an event by considering all possible ways it can occur through different, mutually exclusive scenarios. If \(B_1, B_2, \dots, B_n\) are mutually exclusive and exhaustive events, then for any event A: \(P(A) = \sum_{i=1}^{n} P(A | B_i) P(B_i)\).
  • Complementary Events: Two events are complementary if they are mutually exclusive and exhaustive. If A is an event, its complement \(A^c\) is the event that A does not occur. \(P(A^c) = 1 - P(A)\).

Understanding these concepts is crucial for solving problems involving multiple events and dependencies, like the construction job delay example.

Was this answer helpful?

Important Questions from Probability of Random Experiments

  1. Two cards are drawn successively without replacement from a well-shuffled pack of 52 cards. The probability of drawing two aces is

  2. A biased coin with the probability of getting head equal to \(\frac{1}{4}\) is tossed five times. What is the probability of getting tail in all the first four tosses followed by head ? 

  3. Three dice are thrown. What is the probability that each face shows only multiples of 3 ?

  4. A natural number n is chosen from the first 50 natural numbers. What is the probability that \(n+\frac{50}{n}<50 \) ?

  5. A card is drawn from a well-shuffled deck of 52 cards. What is the probability that it is queen of spade?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App