Statement - I : VED analysis is meant for project maximization. Codes :
Statement - II : Network analysis is independent of planning process.
VED analysis categorizes items (often inventory) based on their importance: Vital, Essential, and Desirable. Its primary goal is optimizing inventory management and resource allocation, not general project maximization. Techniques like PERT or CPM are used for project scheduling and maximizing project outcomes.
Therefore, Statement I is incorrect.
Network analysis techniques, such as PERT (Program Evaluation and Review Technique) and CPM (Critical Path Method), are core components of the project planning process. They help visualize project tasks, dependencies, durations, and critical paths.
These methods are integral to planning and are not independent of it. They provide the structure and timeline for the project plan.
Therefore, Statement II is incorrect.
Since both Statement I and Statement II are incorrect, the correct option reflects this.
Which one of the following information type is NOT included in a skill inventory?
When prices are rising, the LIFO produces
What is the one-month forward price of crude oil trading at $ 70 a barrel when annual interest rate is 6 percent and monthly storage cost amounts to $ 0.60?