Sequentially arrange the following steps which are involved in surveying to build an irrigation structure.

A. Reconnaissance survey

B. Preliminary survey

C. Examine the water availability

D. Final location survey

E. Final survey report

The correct answer is

C, A, B, D, E

Understanding Surveying for Irrigation Structures

Surveying is a fundamental step in any construction project, especially for critical infrastructure like irrigation structures. It involves gathering data about the land's topography, existing features, and potential sites. For an irrigation structure, which relies heavily on water sources, the survey process has a specific sequence to ensure feasibility and optimal design.

Steps in Surveying for Irrigation Structures

Let's examine the given steps:

  • C. Examine the water availability: This is the initial and most crucial step. An irrigation structure is useless without a reliable water source. This step involves assessing rivers, groundwater, rainfall patterns, and other potential water sources in the region.
  • A. Reconnaissance survey: Once water availability is confirmed, a reconnaissance survey is conducted. This is a preliminary inspection of the area to get a general idea of the topography, access routes, potential dam or canal sites, and major physical features. It helps narrow down the possible locations for more detailed investigation.
  • B. Preliminary survey: Following reconnaissance, a more detailed preliminary survey is performed for the promising areas identified. This involves mapping the topography more accurately, collecting data on soil types, geological conditions, and existing infrastructure. This data is used to compare potential sites and choose the most suitable one.
  • D. Final location survey: After the best site is selected based on the preliminary survey, a final location survey is conducted. This survey is highly detailed and precise. It involves laying out the exact position, size, and orientation of the proposed structure (like the dam, canal, pump house, etc.) on the ground. This data is essential for detailed design and construction.
  • E. Final survey report: The last step is compiling all the data, findings, maps, drawings, and recommendations from all phases of the survey into a comprehensive final report. This report serves as the basis for design, approvals, and construction planning.

Sequencing the Survey Steps

Based on the logical flow required for planning an irrigation structure, the steps must follow a specific order:

  1. First, confirm if there is sufficient water available to justify building the structure (C).
  2. Next, perform a general reconnaissance of the area to understand the landscape and potential sites (A).
  3. Then, conduct a more detailed preliminary survey of promising locations to collect specific data and compare options (B).
  4. Once the site is chosen, carry out a precise survey to fix the exact location and layout of the structure (D).
  5. Finally, document all the findings and plans in a comprehensive report (E).

Therefore, the correct sequence is C, A, B, D, E.

Step Activity Purpose
C Examine water availability Confirm existence of sufficient water source.
A Reconnaissance survey Initial site visit, general overview, identify potential areas.
B Preliminary survey Detailed mapping, data collection for comparing sites.
D Final location survey Precise layout of the chosen structure on site.
E Final survey report Documentation of all findings and plans.

This sequence ensures that resources are not wasted on surveying areas where water is scarce and that detailed planning occurs only after a feasible site is identified and precisely located.

Revision Table: Irrigation Survey Sequence

Here is a quick review of the correct order of operations for surveying for an irrigation project:

  • Is there water? (C)
  • Where should we look generally? (A)
  • Which potential site is best based on details? (B)
  • Exactly where does the structure go on the best site? (D)
  • Let's write it all down. (E)

Additional Information: Importance of Each Survey Stage

Each stage of surveying plays a vital role in the success of an irrigation project:

  • Water Availability (C): This initial check prevents investment in non-viable projects. It might involve hydrological studies, well exploration, or rainfall analysis.
  • Reconnaissance (A): Saves time and money by quickly eliminating unsuitable large areas. It often involves visual inspection, existing maps, and talking to local people.
  • Preliminary Survey (B): Provides the detailed technical data needed to compare different options objectively, considering factors like construction costs, land acquisition, and engineering challenges.
  • Final Location Survey (D): Translates the design into reality on the ground, providing the precise points and elevations necessary for accurate construction layout.
  • Final Report (E): Serves as a comprehensive record, a basis for design calculations, cost estimates, and a reference for future maintenance or expansions. It is a key legal and technical document.

Understanding this sequence is key for anyone involved in the planning and execution of water resource projects.

Was this answer helpful?

Important Questions from Dams and Spillways

  1. A drop in canal bed is generally provided, if

  2. ________ is a kind of passage to allow water from upstream to downstream of a dam which has flood gates to control the flow.

  3. In Gravity dam, the factor of safety against overturning should not be less than

  4. For the upstream face of an earthen dam, the most adverse condition for stability of slope is:

  5. For no tension to develop in the gravity dam the resultant of all external forces should always lie _______.

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App