Question

Pessimistic time and optimistic time of completion of an activity are given as 10 days and 4 days respectively, the variance of the activity will be

The correct answer is

1

Calculating Activity Variance in PERT

In project management, specifically using the Program Evaluation and Review Technique (PERT), we often estimate activity durations based on three different time estimates: optimistic time, pessimistic time, and most likely time. These estimates help account for the uncertainty inherent in project activities.

The optimistic time ($T_o$) is the shortest possible time in which the activity can be completed, assuming everything goes perfectly. The pessimistic time ($T_p$) is the longest possible time required to complete the activity, assuming unfavorable conditions.

Based on these estimates, PERT uses formulas to calculate the expected time and the variance of the activity completion time. The variance is a measure of the uncertainty or risk associated with the activity duration. A higher variance indicates greater uncertainty.

PERT Variance Formula

The formula for calculating the standard deviation ($\sigma$) of an activity's duration in PERT is:

$$\sigma = \frac{T_p - T_o}{6}$$

The variance ($\sigma^2$) is the square of the standard deviation:

$$\sigma^2 = \left(\frac{T_p - T_o}{6}\right)^2$$

Step-by-Step Calculation

We are given the following values:

  • Pessimistic time ($T_p$) = 10 days
  • Optimistic time ($T_o$) = 4 days

Now, we can substitute these values into the variance formula:

$$\text{Variance} = \left(\frac{10 \text{ days} - 4 \text{ days}}{6}\right)^2$$

$$\text{Variance} = \left(\frac{6 \text{ days}}{6}\right)^2$$

$$\text{Variance} = (1)^2$$

$$\text{Variance} = 1$$

Result

The variance of the activity completion time is 1.

Parameter Value
Optimistic Time ($T_o$) 4 days
Pessimistic Time ($T_p$) 10 days
Standard Deviation ($\sigma$) $\frac{10-4}{6} = 1$
Variance ($\sigma^2$) $(1)^2 = 1$

Comparing this result with the given options, the variance is 1.

Was this answer helpful?

Important Questions from PERT and CPM

  1. Which one of the following distributions provides information regarding the uncertainty of duration time estimates is PERT described network?

  2. Which of the following distribution represents the time estimates in PERT ?

  3. Negative slack occurs when -

  4. In PERT analysis, the possible number of time estimates for activities linking up two events are -

  5. The amount of time by which an activity can be delayed without affecting project completion time is

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App