Pessimistic time and optimistic time of completion of an activity are given as 10 days and 4 days respectively, the variance of the activity will be
1
In project management, specifically using the Program Evaluation and Review Technique (PERT), we often estimate activity durations based on three different time estimates: optimistic time, pessimistic time, and most likely time. These estimates help account for the uncertainty inherent in project activities.
The optimistic time ($T_o$) is the shortest possible time in which the activity can be completed, assuming everything goes perfectly. The pessimistic time ($T_p$) is the longest possible time required to complete the activity, assuming unfavorable conditions.
Based on these estimates, PERT uses formulas to calculate the expected time and the variance of the activity completion time. The variance is a measure of the uncertainty or risk associated with the activity duration. A higher variance indicates greater uncertainty.
The formula for calculating the standard deviation ($\sigma$) of an activity's duration in PERT is:
$$\sigma = \frac{T_p - T_o}{6}$$
The variance ($\sigma^2$) is the square of the standard deviation:
$$\sigma^2 = \left(\frac{T_p - T_o}{6}\right)^2$$
We are given the following values:
Now, we can substitute these values into the variance formula:
$$\text{Variance} = \left(\frac{10 \text{ days} - 4 \text{ days}}{6}\right)^2$$
$$\text{Variance} = \left(\frac{6 \text{ days}}{6}\right)^2$$
$$\text{Variance} = (1)^2$$
$$\text{Variance} = 1$$
The variance of the activity completion time is 1.
| Parameter | Value |
|---|---|
| Optimistic Time ($T_o$) | 4 days |
| Pessimistic Time ($T_p$) | 10 days |
| Standard Deviation ($\sigma$) | $\frac{10-4}{6} = 1$ |
| Variance ($\sigma^2$) | $(1)^2 = 1$ |
Comparing this result with the given options, the variance is 1.
Which one of the following distributions provides information regarding the uncertainty of duration time estimates is PERT described network?
Which of the following distribution represents the time estimates in PERT ?
Negative slack occurs when -
In PERT analysis, the possible number of time estimates for activities linking up two events are -
The amount of time by which an activity can be delayed without affecting project completion time is