Optimum signal cycle in Webster Method is given by C 0 :

The correct answer is \(C=\dfrac{1.5L+5}{1-Y}\)

Webster Method Optimum Signal Cycle Formula

The Webster Method is a common technique used in traffic engineering to determine the optimum cycle length for a traffic signal at an intersection. The goal is typically to minimize the average delay to vehicles.

The optimum signal cycle length, denoted as \(C_0\) or simply \(C\), is calculated using a specific formula that relates the total lost time per cycle and the sum of critical flow ratios.

The formula for the optimum signal cycle \(C\) in the Webster Method is given by:

\[ C = \frac{1.5L+5}{1-Y} \]

Let's understand the terms in this formula:

  • \(C\) is the optimum signal cycle length in seconds.
  • \(L\) is the total lost time per cycle in seconds. This includes start-up lost time and clearance lost time for all signal phases.
  • \(Y\) is the sum of critical flow ratios for all phases. The critical flow ratio for a phase is the maximum of the flow ratios (actual flow rate / saturation flow rate) for the lane groups within that phase. \(Y\) is the sum of these maximum critical flow ratios across all phases.

Analyzing the Provided Options

We are given four options for the formula of the optimum signal cycle in the Webster Method. Let's compare them with the standard formula:

  • Option 1: \(C=\dfrac{1.5L+10}{1+Y}\) - This formula does not match the standard Webster formula. The numerator constant is different, and the denominator has a plus sign instead of a minus sign.
  • Option 2: \(C=\dfrac{1.5L+5}{1+Y}\) - This formula also does not match the standard Webster formula. While the numerator matches, the denominator has \(1+Y\) instead of \(1-Y\).
  • Option 3: \(C=\dfrac{1.5L+5}{1-Y}\) - This formula exactly matches the standard formula for the optimum signal cycle according to the Webster Method.
  • Option 4: \(C=\dfrac{1.65L+5}{1-Y}\) - This formula is close but uses a constant of \(1.65\) multiplying \(L\) instead of \(1.5\). This is a variation, but the standard Webster formula uses \(1.5L\).

Based on the standard Webster Method formula for the optimum signal cycle, the correct expression is \(C=\dfrac{1.5L+5}{1-Y}\).

Was this answer helpful?

Important Questions from Traffic Engineering

  1. The load in a motorcycle fitted with a light weight container shall not exceed ___________kgs.

  2. Which one of the following is NOT a Tunnel cross section?
  3. As per IRC: 67-2001, a traffic sign indicating the Speed Limit on a road should be of:
  4. As per the IRC guidelines, pedestrian green time is calculated for walking speed of ______.
  5. The diameter of a mandatory sign disc must be

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App