Match the type of indicators given in Column-I with examples given in Column-II.
Column – I Column – II (a) Input Indicator (i) No. of acceptors of family planning services (b) Output Indicator (ii) Beneficiaries attending family planning clinic (c) Outcome Indicator (iii) Births averted due to acceptance of family planning methods (d) Impact Indicator (iv) Supply of various contraceptives
Codes :
a-(ii), b-(iii), c-(iv), d-(i)
Understanding different types of indicators is crucial for program evaluation. Indicators help measure progress towards goals. Let's match the indicator types in Column I with their examples in Column II based on the provided correct answer.
We need to match the following:
The provided correct answer suggests the following matching:
Reasoning: In this context, beneficiaries attending the clinic represents the initial engagement or resources mobilisation, considered an input.
Reasoning: This pairing suggests that 'births averted' is viewed as a direct, immediate result stemming from program activities, hence an output in this specific classification.
Reasoning: Here, the availability or 'supply' of necessary resources like contraceptives is considered a key result or condition achieved by the program, functioning as an outcome.
Reasoning: The number of individuals accepting services is aligned with the broader, long-term effect or 'impact' the program aims to achieve on the population's behaviour.
Based on the matching derived from the provided correct answer (a-ii, b-iii, c-iv, d-i), Option 2 is the correct choice.
Factors which govern the operating cost of an equipment are :
1. Purchase price of the equipment
2. Depreciation due to regular use
3. Cost of operation, maintenance and repairs
Which of the above statements are correct ?
In Emerson's efficiency plan of wage incentive system, the bonus is paid to-
Match List I with List II
LIST I (Project Network concepts) | LIST II (Underlying meaning) | ||
| A. | Crashing an activity | I. | Length of the longest path through the project network |
| B. | Project Network | II. | It shows the time and cost when the activity is fully crashed |
| C. | Critical path | III. | It consists of a number of nodes and a number of arcs that connects two different nodes |
| D. | Crash point | IV. | Taking special (costly) measures to reduce the duration of an activity below its normal value |
Choose the correct answer from the options given below:
The following statements relate to project network. Choose the correct code for the statements being correct or incorrect.
Statement I: An activity cannot be represented by more than one arrow, but an arrow can represent one or more activities.
Statement II : The activities in a critical path can be preponed or postponed.
A public limited company has 9,00,000 shares outstanding at current market price of Rs. 130 per share. The company needs Rs. 2.25 crores to finance its proposed new project. The board of the company has decided to issue rights shares to raise the required money at Rs. 75 per share (as subscription price) to ensure that the rights issue is fully subscribed. How many rights are required to purchase a new share ?