All Exams Test series for 1 year @ ₹349 only
Question

In case of design of a weir or a barrage by providing a higher afflux, the waterway and, therefore, the length of the weir can be reduced, but it will result in

The correct answer is
increased cost of training works

Understanding Weir and Barrage Design with Afflux

When designing a weir or a barrage, engineers need to balance several factors, including the cost of the structure and its impact on the river. One key design parameter is afflux. Afflux is the rise in the water level upstream of a structure like a weir or barrage due to the obstruction it creates in the river flow. By allowing a higher afflux, the required width of the waterway (and thus the length of the weir crest) can potentially be reduced.

A shorter weir means less construction material for the main barrier itself. However, reducing the waterway has significant downstream consequences related to the flow pattern and energy dissipation.

Consequences of Higher Afflux and Reduced Waterway

Reducing the waterway length while passing the same total discharge means that the flow is concentrated over a smaller width. This leads to:

  • Increased velocity of water flowing over or through the structure.
  • Higher energy dissipation downstream of the structure, often resulting in a more turbulent hydraulic jump.
  • Increased discharge intensity (discharge per unit length) across the weir or barrage. The discharge intensity \(q\) is given by the formula: \(q = \frac{Q}{L}\), where \(Q\) is the total discharge and \(L\) is the length of the weir. If \(L\) decreases for a constant \(Q\), \(q\) increases.

Impact on Training Works and Scour

The increased velocity and energy dissipation downstream lead to a greater potential for scour (erosion) of the river bed and banks immediately below the structure. To protect the structure itself, the river banks, and other infrastructure, substantial river training works are necessary.

River training works typically include structures like:

  • Guide banks: Curved structures built upstream and downstream of the weir/barrage to guide the flow smoothly and prevent the river from outflanking the structure.
  • Marginal bunds: Embankments built parallel to the river banks upstream of the weir/barrage to contain the higher water level caused by afflux and protect adjacent land.
  • Aprons and Launching Aprons: Protective layers (like concrete blocks or stones) placed on the river bed downstream of the weir to prevent scour from undermining the structure.

With higher afflux and the resulting increase in velocity, energy, and scour potential, these training works must be more robust, extend further upstream and downstream, and be constructed with stronger materials to withstand the increased forces. This directly leads to an increase in their construction cost.

Analyzing the Options

Let's examine the given options based on the effects of higher afflux and reduced waterway:

Option Analysis Result
Increased cost of training works Higher afflux and reduced waterway lead to increased velocity and scour downstream. Training works like guide banks and aprons need to be larger and stronger to manage this, increasing their cost. Marginal bunds also need to be higher and stronger due to increased upstream water level. Consistent with the consequences.
Reduced risk of failure by outflanking Higher afflux increases the upstream water level. If marginal bunds are not adequately designed for this higher level, the risk of the river flowing around (outflanking) the structure increases, not reduces. Inconsistent with the consequences.
Reduced scour Higher afflux and reduced waterway concentrate the flow, leading to higher velocity and turbulence downstream, which increases scour, not reduces it. Inconsistent with the consequences.
Reduced discharge intensity Discharge intensity is discharge per unit width. Reducing the waterway length means the same total discharge passes through a smaller width, thus increasing the discharge intensity. Inconsistent with the consequences.

Based on the analysis, increasing the afflux to reduce the waterway results in an increased cost of training works due to higher velocities, energy dissipation, and scour potential.

Conclusion

While reducing the length of the weir or barrage by providing a higher afflux might save costs on the main structure, it significantly increases the demands on the river training works required upstream and downstream to manage the altered flow regime and mitigate the risk of scour and outflanking. Therefore, it results in increased cost of training works.

Revision Table: Weir Design Considerations

Design Parameter Effect of Increasing Parameter Notes
Afflux Allows shorter weir/barrage length; Increases upstream water level; Increases downstream flow velocity & scour potential. Higher afflux generally requires more expensive training works.
Weir/Barrage Length (Waterway) Longer length means less afflux (for same discharge); Lower flow velocity & scour potential downstream; Reduces discharge intensity. Longer structures are more expensive for the main body but may reduce training works cost.

Additional Information: Components of Weir and Barrage Costs

The total cost of a weir or barrage project includes several components:

  • Main Structure Cost: Cost of the barrage body, gates, piers, and foundations. Reducing length saves on this.
  • Training Works Cost: Cost of guide banks, marginal bunds, aprons, etc. Higher afflux/shorter waterway increases this cost.
  • Land Acquisition Cost: Cost of land needed for the structure and flooded area due to afflux. Higher afflux may increase upstream land acquisition costs.
  • Energy Dissipation Works Cost: Cost of stilling basins or other structures to manage downstream energy. Increased energy dissipation needs more robust structures.
  • Bridge/Roadway Cost: If a bridge is included over the barrage.

Optimizing the design involves finding a balance between these costs. A design with higher afflux might reduce the main structure cost but increases the training works cost, and vice-versa. The overall minimum cost design considers all these factors.

Was this answer helpful?

Important Questions from Miscellaneous-Engineering

  1. A well foundation of 6 m external diameter and of 5 m internal diameter is sunk to a depth of 15 m in a deep deposit of sand. If the average N value of sand is 20, the load that the well can carry by bearing alone will be nearly
  2. What is the maximum depth to which a trench of vertical sides can be excavated in a clay stratum with c = 50 kN/m², y = 16 kN/m³, β = 90°, ¢ = 0°, Fc = 1 and N = 0-261?

  3. Which one of the following is an example of reinforced earth wall?
  4. Which one of the following data is not required for design of a weir or a barrage?
  5. In case of irrigation canal, the seepage losses depend upon
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App