All Exams Test series for 1 year @ ₹349 only
Question

In a time series forecasting model, the demands for five time periods were 10, 13, 15, 18 and 22. A linear regression fit resulted in an equation F = 6.9 + 2.9t where F is the forecast for period t. The sum of the absolute deviations for the five data is

The correct answer is

2.2

Calculating the Sum of Absolute Deviations in Time Series Forecasting

This problem requires us to calculate the sum of the absolute deviations between the actual demands and the forecasts generated by a linear regression model for a given time series.

Understanding the Data and the Forecast Model

We are given the actual demands for five time periods:

  • Period 1 (t=1): Demand = 10
  • Period 2 (t=2): Demand = 13
  • Period 3 (t=3): Demand = 15
  • Period 4 (t=4): Demand = 18
  • Period 5 (t=5): Demand = 22

The linear regression forecast model is given by the equation: \(F = 6.9 + 2.9t\), where \(F\) is the forecast for time period \(t\).

Steps to Calculate Sum of Absolute Deviations

To find the sum of the absolute deviations, we need to follow these steps:

  1. Calculate the forecast (\(F\)) for each time period (\(t\)) using the given equation.
  2. Calculate the deviation (Error) for each period: Deviation = Actual Demand - Forecast.
  3. Calculate the absolute deviation for each period: |Deviation|.
  4. Sum up the absolute deviations for all five periods.

Calculating Forecasts and Deviations

Let's calculate the forecast, deviation, and absolute deviation for each period:

  • Period 1 (t=1): Forecast \(F_1 = 6.9 + 2.9 \times 1 = 6.9 + 2.9 = 9.8\). Deviation = Actual Demand - Forecast = \(10 - 9.8 = 0.2\). Absolute Deviation = \(|0.2| = 0.2\).
  • Period 2 (t=2): Forecast \(F_2 = 6.9 + 2.9 \times 2 = 6.9 + 5.8 = 12.7\). Deviation = Actual Demand - Forecast = \(13 - 12.7 = 0.3\). Absolute Deviation = \(|0.3| = 0.3\).
  • Period 3 (t=3): Forecast \(F_3 = 6.9 + 2.9 \times 3 = 6.9 + 8.7 = 15.6\). Deviation = Actual Demand - Forecast = \(15 - 15.6 = -0.6\). Absolute Deviation = \(|-0.6| = 0.6\).
  • Period 4 (t=4): Forecast \(F_4 = 6.9 + 2.9 \times 4 = 6.9 + 11.6 = 18.5\). Deviation = Actual Demand - Forecast = \(18 - 18.5 = -0.5\). Absolute Deviation = \(|-0.5| = 0.5\).
  • Period 5 (t=5): Forecast \(F_5 = 6.9 + 2.9 \times 5 = 6.9 + 14.5 = 21.4\). Deviation = Actual Demand - Forecast = \(22 - 21.4 = 0.6\). Absolute Deviation = \(|0.6| = 0.6\).

We can summarize these values in a table:

Period (t) Actual Demand Forecast (F) Deviation (Demand - F) Absolute Deviation (|Deviation|)
1 10 9.8 0.2 0.2
2 13 12.7 0.3 0.3
3 15 15.6 -0.6 0.6
4 18 18.5 -0.5 0.5
5 22 21.4 0.6 0.6

Summing the Absolute Deviations

The final step is to sum the absolute deviations calculated for each period:

Sum of Absolute Deviations = \(0.2 + 0.3 + 0.6 + 0.5 + 0.6\)

Sum of Absolute Deviations = \(2.2\)

Therefore, the sum of the absolute deviations for the five data points is 2.2.

Was this answer helpful?

Important Questions from Forecasting

  1. Name the human resource demand (need) forecasting technique, which solicits estimates of personnel needs from a group of experts, usually managers. The HRP experts act as intermediaries, summarise the various responses and report the findings back to the experts. The experts are surveyed again after they receive this feedback. Summaries and surveys are repeated until the experts' opinions begin to agree. The agreement reached is the forecast of the personnel needs.

    Select the correct option :

  2. The sensitivity of forecast in simple moving average forecasting method, for the increase of the length of average period,

  3. For a product, the forecast and the actual sales for December 2008 were 25 and 20 respectively. If the exponential smoothing constant (α) is taken as 0.2, the forecast sales for January 2009 would be.

  4. For a product the forecast and actual sales for December 2002 were 25 and 20 respectively. If the exponential smoothing constant is taken as 0.2, then forecast sale for January 2003 would be

  5. The difference between the actual demand for any time period and the forecast for the same period is termed as _______.
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App