If the Net Present Value (NPV) of an investment proposal is positive, what conclusions can be drawn? A. The investment generated present value of cashflows exceed cost of investment B. The discount rate used is less than the investments estimated return C. The discount rate used equals the minimum return required by the investors D. The investment generated present value of cashflows equals the cost of investment E. The investment's Internal Rate of Return (IRR) exceeds the Cost of Capital Choose the correct answer from the options given below:
A, B and E only
The question asks what conclusions can be drawn if an investment proposal has a positive Net Present Value (NPV). Let's first understand what NPV means.
Net Present Value (NPV) is a capital budgeting tool used to evaluate the profitability of an investment. It calculates the difference between the present value of cash inflows and the present value of cash outflows over a period of time. The formula is typically given by:
\( \text{NPV} = \sum_{t=0}^{n} \frac{C_t}{(1+r)^t} - C_0 \)
Where:
A positive NPV indicates that the project is expected to generate more cash inflow in present value terms than the cost required to undertake the project. Decision Rule: If NPV > 0, accept the project. If NPV < 0, reject the project. If NPV = 0, the project is expected to earn exactly the required rate of return, making the decision neutral from a purely financial standpoint based on NPV.
Let's examine each statement provided in the options:
Based on the analysis:
The valid conclusions from a positive NPV are A, B, and E.
| Statement | Analysis with Positive NPV | Conclusion (True/False) |
|---|---|---|
| A: PV of cashflows > Cost of investment | Definition of positive NPV | True |
| B: Discount rate < Investment's estimated return | Positive NPV implies project return exceeds discount rate | True |
| C: Discount rate = Minimum required return | This is usually the discount rate, but not a conclusion *from* positive NPV | False (as a conclusion from positive NPV) |
| D: PV of cashflows = Cost of investment | This implies zero NPV, not positive NPV | False |
| E: Investment's IRR > Cost of Capital | Positive NPV at Cost of Capital implies IRR > Cost of Capital | True |
The options provided combine these statements. We are looking for the option that lists A, B, and E.
Let's check the given options:
Therefore, the conclusions that can be drawn if the Net Present Value (NPV) of an investment proposal is positive are that the investment generated present value of cashflows exceed the cost of investment, the discount rate used is less than the investment's estimated return (which can be related to IRR), and the investment's Internal Rate of Return (IRR) exceeds the Cost of Capital.
| Concept | Definition | Decision Rule (using NPV) |
|---|---|---|
| Net Present Value (NPV) | Difference between the present value of future cash inflows and the initial cost. | Accept project if NPV > 0. |
| Discount Rate (r) | The required rate of return or cost of capital used to discount future cash flows back to their present value. | Used in the NPV calculation. |
| Present Value of Cash Flows | The value today of cash flows expected to be received or paid in the future, discounted at a specific rate. | Compared against the initial cost in NPV calculation. |
| Internal Rate of Return (IRR) | The discount rate at which the NPV of an investment is zero. | Compared against the discount rate (Cost of Capital) for decision making (Accept if IRR > Cost of Capital). |
Both NPV and IRR are widely used capital budgeting techniques. They often lead to the same investment decisions, especially for independent projects with conventional cash flows (an initial outflow followed by inflows).
The conclusion from a positive NPV (using the Cost of Capital as the discount rate) that the IRR exceeds the Cost of Capital highlights the strong relationship between these two methods for conventional projects.
A firm is currently earning Rs. 50,000 and its one share has a present market value of Rs. 175. It has 5,000 shares outstanding. The earnings of the firm is expected to remain stable and it has a payout ratio of 100%. The cost of equity is:
With project cost of ₹300 lacs, profits after depreciation (straight line method) and tax for its lifetime of 5 years are estimated at ₹10 lacs, ₹10 lacs, ₹30 lacs, ₹40 lacs and ₹50 lacs respectively. The cost of capital is 12% and discount factors @ 12%, for the first five years are 0.89, 0.80, 0.71, 0.64 and 0.57 respectively. The Net present value of project is :
Match List I with List II
LIST I (Investment Decision rule) | LIST II (Feature) | ||
| A. | NPV | I. | Insufficiently consistent |
| B. | Payback | II. | Highly Inflexible |
| C. | Cash Returns | III. | Balance between flexibility and consistency |
| D. | Accounting Returns | IV. | Relatively consistent |
Choose the correct answer from the options given below:
Arrange (in descending order) the following present value of a growing perpetuity which makes first payment of Rs. 3,000 in next year.
A. Present value at 8% growth and 10% discount rate.
B. Present value at 3% growth and 9% discount rate.
C. Present value at 6% growth and 11% discount rate.
D. Present value at 5% growth and 6% discount rate.
E. Present value at 1% growth and 4% discount rate.
Choose the correct answer from the options given below
In which method of capital budgeting, cash flows are re-invested at the required rate of return?