If the difference in the reduced levels of the end points is H, slope correction for a slope distance 'I' will be
H2 / 2I
In surveying, when measurements are taken along sloping ground, the measured distance (slope distance) is longer than the true horizontal distance. For accurate mapping and calculations, it's essential to convert these slope distances into their corresponding horizontal distances. This conversion involves applying a correction known as slope correction.
When measuring distances on uneven terrain, the tape or chain is held along the slope. However, maps and plans represent features as if projected onto a horizontal plane. Therefore, the measured slope distance needs to be reduced to its equivalent horizontal distance. The difference between the slope distance and the horizontal distance is the slope correction.
Let's consider the following terms in the context of distance measurement on a slope:
These three quantities form a right-angled triangle, where the slope distance 'I' is the hypotenuse, the horizontal distance 'D' is one leg, and the difference in reduced levels 'H' is the other leg.
We can use the Pythagorean theorem to relate these three quantities:
$$\text{I}^2 = \text{D}^2 + \text{H}^2$$
From this, we can express the horizontal distance 'D' as:
$$\text{D}^2 = \text{I}^2 - \text{H}^2$$
$$\text{D} = \sqrt{\text{I}^2 - \text{H}^2}$$
The slope correction ($\text{C}_{\text{s}}$) is defined as the difference between the slope distance and the horizontal distance:
$$\text{C}_{\text{s}} = \text{I} - \text{D}$$
Substitute the expression for 'D':
$$\text{C}_{\text{s}} = \text{I} - \sqrt{\text{I}^2 - \text{H}^2}$$
To simplify this expression, we can factor out $\text{I}^2$ from under the square root:
$$\text{C}_{\text{s}} = \text{I} - \sqrt{\text{I}^2 \left(1 - \frac{\text{H}^2}{\text{I}^2}\right)}$$
$$\text{C}_{\text{s}} = \text{I} - \text{I}\sqrt{1 - \frac{\text{H}^2}{\text{I}^2}}$$
$$\text{C}_{\text{s}} = \text{I}\left(1 - \sqrt{1 - \frac{\text{H}^2}{\text{I}^2}}\right)$$
For small values of $\frac{\text{H}}{\text{I}}$ (which is typically true in practical surveying, meaning the slope is not extremely steep), we can use the binomial approximation:
$$(1 - x)^n \approx 1 - nx \quad \text{for small } x$$
In our case, $x = \frac{\text{H}^2}{\text{I}^2}$ and $n = \frac{1}{2}$.
So, $\sqrt{1 - \frac{\text{H}^2}{\text{I}^2}} = \left(1 - \frac{\text{H}^2}{\text{I}^2}\right)^{\frac{1}{2}} \approx 1 - \frac{1}{2}\left(\frac{\text{H}^2}{\text{I}^2}\right)$
Substitute this approximation back into the equation for $\text{C}_{\text{s}}$:
$$\text{C}_{\text{s}} \approx \text{I}\left(1 - \left(1 - \frac{\text{H}^2}{2\text{I}^2}\right)\right)$$
$$\text{C}_{\text{s}} \approx \text{I}\left(1 - 1 + \frac{\text{H}^2}{2\text{I}^2}\right)$$
$$\text{C}_{\text{s}} \approx \text{I}\left(\frac{\text{H}^2}{2\text{I}^2}\right)$$
$$\text{C}_{\text{s}} \approx \frac{\text{H}^2}{2\text{I}}$$
This is the standard formula for slope correction, which gives the amount by which the slope distance must be reduced to obtain the horizontal distance.
Given the difference in the reduced levels of the end points is $\text{H}$ and the slope distance is $\text{I}$, the slope correction is approximately $\frac{\text{H}^2}{2\text{I}}$. This correction is always subtracted from the slope distance to get the horizontal distance, as the horizontal distance must always be shorter than the slope distance.
Therefore, the correct formula for slope correction is $\text{H}^2 / 2\text{I}$.
Which among the following error represent the limit of precision in the determination of a value & obey the laws of chance and therefore, must be handled according to the mathematical laws of probability?
The number of observations required of an operation to produce results having a specified accuracy
Consider the following statements.
A. Cumulative errors are more important than compensating errors
B. All cumulative errors are equally important
C. The more times a line is measured, the more likely the accidental errors to disappear from mean
D. Variation in temperature results in compensating error
Which of the above statements is/are correct?
Which of these is not a cumulative error while surveying?
While calculating the correction to volume, V=(1+3e)v', e can calculated by: