If 21 May 2009 is Thursday, then what will be the day of the week on 15 July 2017?
Saturday
This problem asks us to find the day of the week for a specific date in the future, given the day of the week for an earlier date. The key to solving such calendar problems is to calculate the total number of "odd days" between the two dates. An odd day is the remainder left after dividing the total number of days by 7 (since there are 7 days in a week).
We are given that 21 May 2009 is a Thursday. We need to find the day on 15 July 2017.
First, let's find the number of odd days over the complete years from 21 May 2009 to 21 May 2017. This is a period of exactly 8 years (2010, 2011, 2012, 2013, 2014, 2015, 2016, 2017). We need to identify the leap years within this period.
Leap years between 2009 and 2017 (inclusive of the period covered):
There are 2 leap years and 8 - 2 = 6 ordinary years in this period.
Total odd days from 21 May 2009 to 21 May 2017:
To find the net effect on the day of the week, we find the remainder when 10 is divided by 7:
Odd days = $10 \pmod{7} = 3$
So, 21 May 2017 will be 3 days after Thursday.
Thursday + 3 days = Friday, Saturday, Sunday.
Therefore, 21 May 2017 is a Sunday.
Now we need to calculate the number of odd days from 21 May 2017 to 15 July 2017.
Let's find the odd days for each month:
Total odd days from 21 May 2017 to 15 July 2017 = $3 + 2 + 1 = 6$ days.
We found that 21 May 2017 is a Sunday. We need to add the odd days calculated in Step 2 to this day.
Day on 15 July 2017 = Day on 21 May 2017 + Total odd days from May to July
Day on 15 July 2017 = Sunday + 6 days
Counting 6 days after Sunday: Monday, Tuesday, Wednesday, Thursday, Friday, Saturday.
So, 15 July 2017 is a Saturday.
| Period | Total Days/Odd Days | Odd Days $\pmod{7}$ |
|---|---|---|
| 21 May 2009 to 21 May 2017 (8 years) | 6 Ordinary Years (6 odd days) + 2 Leap Years (4 odd days) = 10 odd days | $10 \pmod{7} = 3$ |
| 21 May 2017 to 15 July 2017 | May (10 days) + June (30 days) + July (15 days) = 55 days | $55 \pmod{7} = 6$ |
Alternative calculation: Add total odd days from both steps:
Total odd days from 21 May 2009 to 15 July 2017 = Odd days (years) + Odd days (months)
Total odd days = $3 + 6 = 9$
Net odd days = $9 \pmod{7} = 2$
Starting day was Thursday. Add 2 days:
Thursday + 2 days = Friday, Saturday.
So, 15 July 2017 is a Saturday.
| Concept | Explanation |
|---|---|
| Ordinary Year | 365 days (1 odd day) |
| Leap Year | 366 days (2 odd days), occurs every 4 years (except for years divisible by 100 but not by 400) |
| Odd Days | The remainder when the total number of days is divided by 7. This determines the shift in the day of the week. |
| Calculating Odd Days | Sum up odd days from years and months in the period. Find the total odd days modulo 7. Add this number to the starting day's position (e.g., Sunday=0, Monday=1, ... Saturday=6). |
Calendar problems often involve calculating the number of days between two dates and then finding the corresponding day of the week. Here are some helpful points:
If 19 July 2000 was a Wednesday, then what would be the day of the week on 15 June 2012?
What day of the week was 31 st January 2007?
What was the day of the week on 10 June 2011?
What day of the week was 5 February 2008?
What day of the week was 29 June 2010?