All Exams Test series for 1 year @ ₹349 only
Question

Find the expected time of an activity with Pessimistic time (tp) = 14 days, Most likely time (tm) = 8 days, Optimistic time (to) = 2 days.

The correct answer is

8

To find the expected time of an activity, we can use the formula from the Program Evaluation and Review Technique (PERT). PERT considers three time estimates for an activity: optimistic time ($t_o$), most likely time ($t_m$), and pessimistic time ($t_p$).

Understanding the PERT Expected Time Formula

The formula for calculating the expected time ($T_e$) of an activity in PERT is:

$$T_e = \frac{t_o + 4t_m + t_p}{6}$$

This formula gives more weight to the most likely time ($t_m$) compared to the optimistic ($t_o$) and pessimistic ($t_p$) times, reflecting its higher probability of occurrence.

Calculating the Expected Time for the Activity

We are given the following time estimates for the activity:

  • Pessimistic time ($t_p$) = 14 days
  • Most likely time ($t_m$) = 8 days
  • Optimistic time ($t_o$) = 2 days

Now, let's substitute these values into the PERT expected time formula:

$$T_e = \frac{t_o + 4t_m + t_p}{6}$$

$$T_e = \frac{2 \text{ days} + 4 \times 8 \text{ days} + 14 \text{ days}}{6}$$

First, calculate $4 \times t_m$:

$$4 \times 8 = 32 \text{ days}$$

Next, add all the terms in the numerator:

$$2 + 32 + 14 = 48 \text{ days}$$

Finally, divide the sum by 6:

$$T_e = \frac{48 \text{ days}}{6}$$

$$T_e = 8 \text{ days}$$

Summary of Expected Time Calculation

Using the PERT formula with the provided optimistic, most likely, and pessimistic times, the calculated expected time for the activity is 8 days.

The steps were:

  1. Identify the given optimistic time ($t_o$), most likely time ($t_m$), and pessimistic time ($t_p$).
  2. Use the PERT formula: $T_e = (t_o + 4t_m + t_p) / 6$.
  3. Substitute the given values into the formula.
  4. Perform the calculation to find the expected time ($T_e$).

Based on the calculation, the expected time for the activity is 8 days.

Was this answer helpful?

Important Questions from PERT and CPM

  1. Which one of the following distributions provides information regarding the uncertainty of duration time estimates is PERT described network?

  2. Which of the following distribution represents the time estimates in PERT ?

  3. Negative slack occurs when -

  4. In PERT analysis, the possible number of time estimates for activities linking up two events are -

  5. The amount of time by which an activity can be delayed without affecting project completion time is

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App