Find the expected time of an activity with Pessimistic time (tp) = 14 days, Most likely time (tm) = 8 days, Optimistic time (to) = 2 days.
8
To find the expected time of an activity, we can use the formula from the Program Evaluation and Review Technique (PERT). PERT considers three time estimates for an activity: optimistic time ($t_o$), most likely time ($t_m$), and pessimistic time ($t_p$).
The formula for calculating the expected time ($T_e$) of an activity in PERT is:
$$T_e = \frac{t_o + 4t_m + t_p}{6}$$
This formula gives more weight to the most likely time ($t_m$) compared to the optimistic ($t_o$) and pessimistic ($t_p$) times, reflecting its higher probability of occurrence.
We are given the following time estimates for the activity:
Now, let's substitute these values into the PERT expected time formula:
$$T_e = \frac{t_o + 4t_m + t_p}{6}$$
$$T_e = \frac{2 \text{ days} + 4 \times 8 \text{ days} + 14 \text{ days}}{6}$$
First, calculate $4 \times t_m$:
$$4 \times 8 = 32 \text{ days}$$
Next, add all the terms in the numerator:
$$2 + 32 + 14 = 48 \text{ days}$$
Finally, divide the sum by 6:
$$T_e = \frac{48 \text{ days}}{6}$$
$$T_e = 8 \text{ days}$$
Using the PERT formula with the provided optimistic, most likely, and pessimistic times, the calculated expected time for the activity is 8 days.
The steps were:
Based on the calculation, the expected time for the activity is 8 days.
Which one of the following distributions provides information regarding the uncertainty of duration time estimates is PERT described network?
Which of the following distribution represents the time estimates in PERT ?
Negative slack occurs when -
In PERT analysis, the possible number of time estimates for activities linking up two events are -
The amount of time by which an activity can be delayed without affecting project completion time is