All Exams Test series for 1 year @ ₹349 only
Question

Earliest finish of an activity is always:

The correct answer is
Less than or equal to earliest event of the following node

Activity Timing: Earliest Start (ES) and Earliest Finish (EF)

In project management, particularly when using techniques like the Critical Path Method (CPM), understanding the timing of activities is crucial. Two key terms are:

  • Earliest Start (ES): The earliest possible time an activity can begin.
  • Earliest Finish (EF): The earliest possible time an activity can be completed.

The relationship between ES and EF for any single activity is defined as:

$ EF = ES + \text{Duration} $

Where 'Duration' is the time required to complete the activity.

Activity EF Relation to Following Node ES

The question asks for the relationship between the Earliest Finish (EF) of a specific activity and the Earliest Start (ES) time associated with the 'following node'. In network diagrams, an activity connects a start node to an end node. The 'following node' refers to the node where the activity finishes, and from which subsequent activities might start.

Let's consider an activity, Activity A, which finishes at Node N. Let the Earliest Finish time of Activity A be denoted as $EF_A$.

Now, let's consider the 'earliest event of the following node'. This typically refers to the Earliest Start (ES) time of any activity that begins at Node N. Let's call the first activity starting from Node N as Activity B, so its Earliest Start time is $ES_B$.

Predecessor-Successor Relationships Impact on ES

The Earliest Start time ($ES$) of any node (or any activity starting from that node) is determined by the latest Earliest Finish ($EF$) time among all the activities that immediately precede it.

Scenario 1: Single Predecessor

If Activity A is the *only* activity leading into Node N:

$ ES_B = EF_A $

In this specific case, the Earliest Finish of Activity A is equal to the Earliest Start of the next activity.

Scenario 2: Multiple Predecessors

If Node N has multiple predecessor activities (e.g., Activity A and Activity P), the Earliest Start time for Node N (and thus for Activity B starting from it) is the *maximum* of the Earliest Finish times of all its predecessors:

$ ES_B = \max(EF_A, EF_P, ...) $

In this more general scenario, consider the relationship between $EF_A$ (the Earliest Finish of one specific predecessor, Activity A) and $ES_B$ (the Earliest Start of the activity following Node N):

$ EF_A \le \max(EF_A, EF_P, ...) $

Therefore:

$ EF_A \le ES_B $

Activity Timing Conclusion: EF vs ES

The Earliest Finish ($EF$) of a specific activity must be less than or equal to the Earliest Start ($ES$) time of the node it feeds into, because the node's ES is determined by the latest finishing predecessor. Even if the activity in question is the latest finishing predecessor, the equality holds. If it finishes earlier than another predecessor, the inequality is strict.

Thus, the Earliest Finish of an activity is always Less than or equal to the Earliest Start time associated with the node it feeds into (which dictates the Earliest Start of the next activity).

Was this answer helpful?

Important Questions from Mixed Topic (CUET PG)

  1. Which of the following variables are included in the Human Poverty Index?
    (A). The probability of not surviving till the age of 40.
    (B). The adult illiteracy rate.
    (C). The number of people who do not have access to clean water.
    (D). The number of small children who are underweight.
    Choose the correct answer from the options given below:
  2. Which of the following powers and responsibility are delegated to Panchayats?
    (A). to prepare plans and schemes for economic development
    (B). to promote schemes that will enhance social justice
    (C). to levy, collect and appropriate taxes, duties, tolls and fees
    (D). to help in the devolution of governmental responsibilities especially that of finances to local authorities
    Choose the correct answer from the options given below:
  3. Identify the sequence of art forms in India from East to West:
    (A). Bhaona
    (B). Jatra
    (C). Ramlila
    (D). Dashavatar
    (E). Maach
    Choose the correct answer from the options given below:
  4. Which of the following ideas does the concept of 'Sustainability' in Human Development refer to ?
    (A). Continuity in the availability of opportunities.
    (B). Each future generation must have higher opportunities (At least double) than their previous generation.
    (C). All environmental, financial and human resources must be used keeping in mind the future
    (D). Each generation must ensure the availability of choices and opportunities to its future generations.
    Choose the correct answer from the options given below:
  5. The sequence of stages in active listening is
    (A). Understanding
    (B). Remembering
    (C). Responding
    (D). Receiving
    (E) Evaluating

    Choose the correct answer from the options given below:
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App