All Exams Test series for 1 year @ ₹349 only
Question

During maintenance of the track, which of the following problems can be corrected by tightening the fish bolts properly?

The correct answer is

Buckling of track

Understanding Railway Track Maintenance

Railway track maintenance is essential for ensuring the safety, stability, and smooth operation of trains. Various components of the track, such as rails, sleepers, ballast, and fastening systems like fish bolts and fish plates, require regular inspection and maintenance. Problems can arise at rail joints, which are critical areas where two lengths of rail are connected.

Role of Fish Bolts in Track Joints

Rail joints are typically made using two fish plates placed on either side of the rail web and fastened together with fish bolts. These fish bolts pass through holes in the fish plates and the rails. The primary function of the fish bolts and fish plates is to hold the rail ends together securely, ensuring continuity of the rail and allowing for proper transfer of load from one rail to the next.

Proper tightening of the fish bolts is crucial for the effective functioning of the rail joint. If the fish bolts are too loose, the joint becomes weak and unstable. If they are excessively tight, it can restrict the intended movement at expansion joints.

Understanding Common Track Problems

Let's look at the common problems mentioned in the options:

  • Riding Joint: This refers to a condition at the rail joint that causes a rough ride for trains. It is often due to issues like battered rail ends (wear at the rail head) or an uneven surface at the joint. While proper joint maintenance is generally beneficial, tightening fish bolts alone does not directly correct battered rail ends.
  • Pumping Joint: This problem occurs when the ballast beneath the rail joint becomes loose or saturated with water, causing the joint to move vertically under passing trains. This movement pumps fine material out from under the sleepers or ballast. It's primarily a problem with the ballast and formation, not directly corrected by tightening fish bolts, although a stable joint is part of overall good track condition.
  • Buckling of Track: Track buckling is a severe form of track misalignment where the track moves laterally (sideways) under compressive stress, often during hot weather. This happens when thermal expansion of the rails creates high compressive forces that exceed the track's resistance to lateral displacement.
  • Blowing Joint: Similar to a pumping joint, a blowing joint involves the forceful ejection of fine material from the ballast under traffic, often accompanied by air or water. It indicates instability and poor support at the joint, primarily a ballast issue.

Fish Bolts and Track Buckling Connection

While the primary correction for track buckling (lateral displacement) involves realigning the track and potentially cutting rails to relieve stress, proper maintenance of fish bolts plays a significant role in preventing conditions that lead to buckling and maintaining track stability, which is crucial during and after addressing buckling.

  • Fish bolts ensure that the rail joint functions correctly, allowing controlled expansion and contraction of the rails through the designed gap.
  • If fish bolts are loose, the joint integrity is compromised. This can lead to excessive movement, uneven stress distribution, and reduced lateral restraint, potentially contributing to the buildup of compressive stresses that cause buckling, especially in high temperatures.
  • Maintaining proper fish bolt tightness ensures that the track structure behaves as intended, helping it withstand the thermal forces that can lead to buckling.

Therefore, while tightening fish bolts doesn't fix the physical lateral displacement of an already buckled track, it is a critical maintenance activity for preserving track stability and preventing the conditions that can lead to buckling. It is also a necessary step in restoring track integrity during the repair process after buckling has occurred.

Summary of Problem Correction

Reviewing the relationship between tightening fish bolts and the problems:

Problem Relationship with Tightening Fish Bolts
Riding Joint Minor improvement possible by stabilising joint, but doesn't fix root causes like battered ends.
Pumping Joint Indirectly related (stable joint is better), but primarily a ballast/formation issue.
Buckling of Track Crucial for maintaining joint integrity and track stability, helping to prevent buckling and essential during correction/repair.
Blowing Joint Indirectly related, but primarily a ballast/formation issue.

Based on the critical role of fish bolt tightness in maintaining track stability and managing the thermal stresses that contribute to buckling, proper tightening of fish bolts is most directly associated with addressing factors related to track buckling among the given options, even if it's more preventative or part of the correction process rather than a direct standalone fix for existing lateral displacement.

Track Maintenance Revision Table

Track Component Maintenance Activity Example Problem Prevented/Addressed
Fish Bolts Tightening Joint weakness, potential contribution to buckling
Ballast Tamping, Cleaning Pumping/Blowing joints, poor drainage
Rails Grinding, Replacement Battered ends (riding joint), wear
Sleepers Replacement, Packing Poor support, track misalignment

Additional Track Maintenance Information

Track maintenance involves a variety of activities performed regularly to keep the railway track in good condition. These activities can range from routine inspections and minor adjustments to major repairs and renewals. The goal is to ensure the track provides a safe and smooth ride, can carry the intended loads, and resists environmental stresses.

Key aspects of track maintenance include:

  • Inspection: Regular visual checks and automated detection using special trains to identify defects.
  • Correction of Alignment and Level: Using machines like tampers to pack ballast and correct the vertical and horizontal position of the track.
  • Rail Maintenance: Grinding rails to remove surface defects and restore profile, welding rail joints to create continuous welded rail (CWR), and replacing worn-out rails.
  • Joint Maintenance: Ensuring fish plates and bolts are in good condition and properly tightened at jointed track locations.
  • Ballast Maintenance: Cleaning, replenishing, and tamping the ballast to provide adequate support and drainage.
  • Component Replacement: Replacing worn or damaged sleepers, fastenings, and other track components.

Proper maintenance, including the correct tightening of fish bolts, is crucial for the overall resilience of the track structure against forces from traffic and environment, such as the thermal expansion that can lead to track buckling.

Was this answer helpful?

Important Questions from Miscellaneous

  1. Which of the following is NOT a state function or state variable in a thermodynamic system?

  2. What is the full form for "BPL" in Socio-economic aspects?
  3. In October 2024, which of the following companies was awarded the contract for design, manufacturing and commissioning of two high-speed trainsets by Integral Coach Factory (ICF) to be used in India's first bullet train between Mumbai and Ahmedabad?
  4. Which of the following methods of reproduction simply involves the splitting of the parent cell into two daughter cells in the bacteria?
  5. A, B, C and D opened shopping complexes in the same city. The shopping complex of A is 6 km west of the shopping complex of B. The shopping complex of C is 4 km north of the shopping complex of B. The shopping complex of D is 6 km west of the shopping complex of C. In which direction is the shopping complex of D from the shopping complex of A?
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App