CPM method was given by :
Kelly and Walker
The Critical Path Method (CPM) is a fundamental project management technique. It is designed to help project managers identify the sequence of tasks that directly impact the project's completion time. Tasks lying on this sequence are called 'critical tasks', and the sequence itself is the 'critical path'. Any delay in these critical tasks directly delays the entire project.
The CPM technique was pioneered and developed by J. E. Kelly and M. R. Walker. They were working for the DuPont company in the United States during the late 1950s. Their objective was to find a better way to manage the complex maintenance schedules and construction projects undertaken by the company.
While other individuals listed are significant figures in project management and related fields, they are not credited with the initial development of the CPM method:
In summary, the development of the Critical Path Method (CPM) is attributed to the innovative work of Kelly and Walker at DuPont.
Factors which govern the operating cost of an equipment are :
1. Purchase price of the equipment
2. Depreciation due to regular use
3. Cost of operation, maintenance and repairs
Which of the above statements are correct ?
In Emerson's efficiency plan of wage incentive system, the bonus is paid to-
Match List I with List II
LIST I (Project Network concepts) | LIST II (Underlying meaning) | ||
| A. | Crashing an activity | I. | Length of the longest path through the project network |
| B. | Project Network | II. | It shows the time and cost when the activity is fully crashed |
| C. | Critical path | III. | It consists of a number of nodes and a number of arcs that connects two different nodes |
| D. | Crash point | IV. | Taking special (costly) measures to reduce the duration of an activity below its normal value |
Choose the correct answer from the options given below:
The following statements relate to project network. Choose the correct code for the statements being correct or incorrect.
Statement I: An activity cannot be represented by more than one arrow, but an arrow can represent one or more activities.
Statement II : The activities in a critical path can be preponed or postponed.
A public limited company has 9,00,000 shares outstanding at current market price of Rs. 130 per share. The company needs Rs. 2.25 crores to finance its proposed new project. The board of the company has decided to issue rights shares to raise the required money at Rs. 75 per share (as subscription price) to ensure that the rights issue is fully subscribed. How many rights are required to purchase a new share ?