All Exams Test series for 1 year @ ₹349 only
Question

As per Section 73 of the Indian Contract Act, 1872, in estimating the loss or damage arising from a breach of contract, what must be taken into account?

The correct answer is
The means of remedying the inconvenience caused by the non-performance

Understanding Section 73: Estimating Loss from Breach of Contract

Section 73 of the Indian Contract Act, 1872, provides the rules for awarding compensation to parties who have suffered damages due to a breach of contract. When a contract is broken, the party who suffers the loss is entitled to receive compensation from the party who broke the contract. This compensation should be for any loss or damage that naturally arose in the usual course of things from such breach.

Principle of Estimating Damages

The core principle is to place the injured party, as far as money can do it, in the same position they would have been if the contract had been performed. However, Section 73 also incorporates the crucial concept of the injured party's duty to mitigate their losses.

The Role of Remedying Inconvenience

When estimating the loss or damage, the law considers the actions taken or that could have been reasonably taken by the injured party to lessen the impact of the breach. This is reflected in Option 1:

  • The means of remedying the inconvenience caused by the non-performance: This is a critical factor. The law expects the injured party to take reasonable steps to mitigate or minimize the loss they suffer due to the breach. If the injured party could have easily remedied the inconvenience or loss but failed to do so, the compensation awarded might be reduced. For example, if a supplier fails to deliver goods, the buyer is expected to make reasonable efforts to source similar goods elsewhere rather than letting the losses escalate indefinitely.

Why Other Options Are Less Accurate

Let's look at why the other options are not the primary focus when estimating damages under Section 73:

  • The causes which added to the inconvenience: While the causes of the breach are important, Section 73 focuses on the *consequences* (loss/damage) and how they are measured, not just the contributing factors to the inconvenience itself.
  • The factors which has led to the loss: This is too broad. Section 73 specifies that compensation is for loss or damage *as naturally arose* from the breach, implying a direct and foreseeable link, and subject to the injured party's duty to mitigate. It's not just about any factor that led to a loss.
  • The factors which were offered to compensate the loss: The emphasis is on the injured party's actions (or lack thereof) to remedy the situation, not necessarily on offers made by the breaching party, unless such offers were accepted and relevant to the mitigation efforts. The duty to mitigate lies with the injured party.

Conclusion

Therefore, according to Section 73 of the Indian Contract Act, 1872, a key element in estimating the loss or damage arising from a breach of contract is considering the means of remedying the inconvenience caused by the non-performance, highlighting the principle of mitigation of damages.

Was this answer helpful?

Important Questions from Indian contract acts, 1872

  1. Which is the term used for a contract where both the parties to the contract have fulfilled their obligations under the contract?

  2. Which older legislation is proposed to be repealed by the Mussalman Wakf (Repeal) Bill, 2025?
  3. As per the Indian Contract Act, 1872, the revocation of a continuing guarantee by the death of a surety operates:

  4. Which one of the following is not a Contract of Indemnity?
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App