Arrange the operations in production planning and control in correct sequence :

(i) Routing

(ii) Dispatching

(iii) Follow up

(iv) Scheduling

Choose the correct answer from the code given below:

The correct answer is (i), (iv), (ii), (iii)

Understanding Production Planning and Control Operations Sequence

Production planning and control involve several key operations that must be performed in a specific sequence to ensure efficient and timely production. Let's break down the operations mentioned and their logical order in a typical manufacturing process.

The operations listed are:

  1. Routing
  2. Dispatching
  3. Follow up
  4. Scheduling

Let's define each term in the context of production planning and control:

  • Routing: This is the first step in planning the production process. It involves determining the path or sequence of operations that a product will follow from raw material to finished good. It specifies what operations will be performed, where (which machine or workstation), and in what order.
  • Scheduling: Once the route is determined, scheduling comes into play. This involves fixing the time and date for performing each operation specified in the routing. It sets deadlines and allocates time for each stage of production, considering machine availability, labor, and delivery requirements.
  • Dispatching: This is the action phase. It involves initiating the production process according to the production plan (routing and scheduling). This includes issuing orders, instructions, materials, tools, and necessary documents to start the work on the shop floor.
  • Follow up: Also known as expediting, this is the monitoring and control phase. It involves checking the progress of work, identifying deviations from the plan (delays, bottlenecks, quality issues), and taking corrective actions to ensure production stays on track.

Establishing the Correct Sequence

Based on the definitions, the logical flow of these operations is as follows:

  1. You must first decide the path or route the product will take through the factory. This is Routing.
  2. After knowing the route, you need to set the timings and deadlines for each step on that route. This is Scheduling.
  3. With the route and schedule ready, you can now issue instructions and materials to start the actual work. This is Dispatching.
  4. As the work progresses, you need to continuously check if everything is going according to the plan and fix any problems that arise. This is Follow up.

Therefore, the correct sequence of these operations in production planning and control is Routing, followed by Scheduling, then Dispatching, and finally Follow up.

Mapping this back to the given list:

  • (i) Routing
  • (iv) Scheduling
  • (ii) Dispatching
  • (iii) Follow up

The correct sequence is (i), (iv), (ii), (iii).

Let's look at this sequence in a simple table:

Order Operation Description
1st (i) Routing Determining the path of production.
2nd (iv) Scheduling Fixing the timeline for each step.
3rd (ii) Dispatching Starting the work according to the plan.
4th (iii) Follow up Monitoring progress and taking action.

This sequence ensures that the production process is planned properly (Routing and Scheduling) before it is initiated (Dispatching) and continuously monitored for deviations (Follow up).

Revision Table: Production Planning & Control Operations

Operation Key Activity Sequence Step
Routing Define 'Where' & 'How' production happens First
Scheduling Define 'When' production happens Second
Dispatching Initiate the planned work Third
Follow up Check progress & correct deviations Fourth

Additional Information: Importance of Production Planning and Control

Production Planning and Control (PPC) is crucial for efficient manufacturing. It aims to produce goods of the right quality, in the right quantity, at the right time, and at the right manufacturing cost. The systematic sequence of operations like Routing, Scheduling, Dispatching, and Follow up helps in:

  • Optimizing resource utilization (machines, labor, materials).
  • Minimizing production time and costs.
  • Ensuring timely delivery to customers.
  • Improving product quality.
  • Reducing waste and scrap.
  • Providing better coordination among different departments.

These operations are interconnected. Poor routing can make scheduling difficult, inefficient dispatching can disrupt the schedule, and inadequate follow-up can lead to delays and quality issues, ultimately affecting the entire production plan.

Was this answer helpful?

Important Questions from Operations Research

  1. A transportation problem with m origins and n destinations becomes a trans-shipment problem with

  2. Match List I with List II

    List I

    List II

    A.

    Markovian property

    I.

    Rule of determining the order in which members of the queue are selected to begin service

    B.

    Waiting time in system

    II.

    The time of next arrival is completely uninfluenced by when the last arrival occurred

    C.

    Steady state condition

    III.

    The queueing is in after operating for some time with a fixed utilisation factor less than one

    D.

    Queue discipline

    IV.

    Elapsed time that an individual customer spends in queue, both before service and during service

    Choose the correct answer from the options given below:

  3. Customers arrive at a reception counter at an average interval rate of 10 minutes and the receptionist takes an average of 6 minutes for one customer. The average queue length is:

  4. The first and foremost important feature for a project to be successful is:

  5. In Queuing Theory, statistical pattern by which customers arrive over a period of time, follows

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App