Arrange the following types of testing in the order they are usually performed in the software Development life cycle.
A. Integration testing
B. Unit testing
C. System Testing
D. Acceptance Testing
Choose the correct answer from the options given below:

The correct answer is
B, A, C, D

Understanding Software Testing Order in SDLC

The question asks to arrange the common stages of software testing in the sequence they typically appear within the Software Development Life Cycle (SDLC). Understanding this order is crucial for building robust and reliable software.

Testing Stages Explained

Let's break down each testing type and its usual place:

B. Unit Testing

Unit Testing focuses on the smallest testable parts of an application, called units (like functions or methods). Developers usually perform this testing during the coding phase to ensure each individual piece works correctly before combining them.

A. Integration Testing

Integration Testing comes after unit testing. It verifies that different units or modules of the software work together as intended when combined. The goal is to expose faults in the interfaces and interactions between integrated components.

C. System Testing

System Testing evaluates the complete and fully integrated software system. This testing is performed from the user's perspective, checking if the entire system meets the specified requirements. It occurs after integration testing.

D. Acceptance Testing

Acceptance Testing is typically the final phase. It's performed by the end-users or stakeholders to confirm that the system meets their business needs and requirements and is ready for deployment. It validates the system's readiness for delivery.

Correct Testing Sequence

Based on the explanations, the standard order for performing these testing types in the SDLC is:

  1. Unit Testing (B): Testing individual components.
  2. Integration Testing (A): Testing combined components.
  3. System Testing (C): Testing the entire integrated system.
  4. Acceptance Testing (D): User validation before deployment.

Therefore, the correct sequence is B, A, C, D.

Final Answer Derivation

Comparing the determined sequence (B, A, C, D) with the given options:

  • Option 1: B, C, A, D
  • Option 2: B, A, C, D
  • Option 3: C, B, A, D
  • Option 4: C, B, D, A

The sequence B, A, C, D matches Option 2.

Was this answer helpful?

Important Questions from Software Testing

  1. Which of the following is/are the types of testing?

  2. Alpha and Beta testing are forms of

  3. Fault base testing technique is

  4. Which of the following is/are behavioral testing technique(s) ?

    (A) Equivalence Partitioning

    (B) Graph-Based Teating Method

    (C) Boundery Value Analysis

    (D) Data flow Testing

    (E) Loop Testing

    Choose the correct answer from the options given below:

  5. In software testing, beta testing is the testing performed by _______.

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App