(a) Determine time sequence
(b) List all the items to be included grouping under flexible and inflexible activities
(c) Bring total estimated time needed and total available time into harmony
(d) Write out plan
(e) Set out as accurate an estimate for each task as is obtainable
Arranging the steps for making time plans involves a logical progression from initial identification to final documentation. The correct sequence ensures efficiency and effectiveness in planning.
The process follows these key stages:
Therefore, the proper sequence is (b), (e), (c), (a), (d).
The correct order, matching Option C, is:
Pick up the correct statement from the following.
Miscellaneous expenses such as office expenses, stationery, postal expenses, etc., falls under _______.
Which of the following phases does NOT come under the project management stages?
The maximum amount of time that an activity can be delayed without extending the completion time of the overall project is called:
A company has 5,000 obsolete toys in inventory at a production cost of $10 each. If the toys were remade for $ 3 each, they could sell for $ 5 each. If the toys are thrown away, they can be sold for $ 2.5 each. Which alternative is more desirable (rework or scrap) and what is the total benefit amount of this alternative?