An Ultrasonic Pulse Velocity (UPV) test was done on a hardened concrete element using a direct transmission method as per IS 516 (Part 5/Section 1): 2018. The distance between the transducer and receiver was 600 mm. The time taken for the induced wave to travel this distance is measured as 0.18 milliseconds. Based on the following Table, the concrete quality grading is ________.
Velocity (km/s) – cross probingConcrete quality grading
Above 4.4Excellent
3.75 – 4.4Good
3.0 – 3.75Doubtful
Less than 3.0Poor

The correct answer is
Doubtful

UPV Test: Problem Setup

The Ultrasonic Pulse Velocity (UPV) test uses the time of travel of an induced wave to assess concrete quality. Key parameters given are:

  • Distance between transducers, $L = 600 \text{ mm} = 0.6 \text{ m}$
  • Time of travel, $t = 0.18 \text{ milliseconds} = 0.18 \times 10^{-3} \text{ s}$
  • Test Method: Direct transmission as per IS 516 (Part 5/Section 1): 2018

UPV Test: Velocity Calculation

The pulse velocity ($V$) is calculated using the formula:

$V = \frac{L}{t}$

Substituting the given values:

$V = \frac{0.6 \text{ m}}{0.18 \times 10^{-3} \text{ s}}$

$V = \frac{0.6}{0.00018} \text{ m/s}$

$V \approx 3333.33 \text{ m/s}$

Converting the velocity to km/s:

$V \approx 3.33 \text{ km/s}$

UPV Test: Concrete Quality Grading

The calculated velocity is compared against the standard grading table provided in IS 516 (Part 5/Section 1): 2018.

Velocity (km/s) Concrete quality grading
Above 4.4 Excellent
3.75 – 4.4 Good
3.0 – 3.75 Doubtful
Less than 3.0 Poor

The calculated velocity $V \approx 3.33 \text{ km/s}$ falls within the range of 3.0 – 3.75 km/s.

Therefore, based on the UPV test results, the concrete quality grading is Doubtful.

Was this answer helpful?

Important Questions from Building Material Characteristics

  1. The correct sequence of stages during firing/burning of bricks is
  2. Rebound hammer test is used to measure
  3. Which of the following statements are true with respect to surface paint?
  4. The stone used in the construction of Kailasa temple at Ellora is
  5. In one litre of paint, volume of solid pigment and volume of non-volatile binder are 400 cc and 600 cc respectively. The Pigment Volume Concentration number of the paint is_______

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App