An optimum project schedule implies
Lowest possible cost and shortest possible time for project
An optimum project schedule is a critical aspect of successful project management. It represents the most efficient plan for completing a project, considering various factors like resources, time, and cost. The goal of an optimum project schedule is to find the best balance that leads to project success.
When we talk about an optimum project schedule, it implies achieving the project goals in the most efficient manner possible. This efficiency is typically measured by two primary factors: the time taken to complete the project and the cost incurred. Therefore, an optimum schedule aims to minimize both, or find the best trade-off between them.
In summary, an optimum project schedule focuses on achieving the project's objectives by balancing the twin goals of minimizing project cost and reducing project completion time. This often involves finding a trade-off where neither cost nor time is sacrificed excessively, leading to the most efficient and effective project completion.
Factors which govern the operating cost of an equipment are :
1. Purchase price of the equipment
2. Depreciation due to regular use
3. Cost of operation, maintenance and repairs
Which of the above statements are correct ?
In Emerson's efficiency plan of wage incentive system, the bonus is paid to-
Match List I with List II
LIST I (Project Network concepts) | LIST II (Underlying meaning) | ||
| A. | Crashing an activity | I. | Length of the longest path through the project network |
| B. | Project Network | II. | It shows the time and cost when the activity is fully crashed |
| C. | Critical path | III. | It consists of a number of nodes and a number of arcs that connects two different nodes |
| D. | Crash point | IV. | Taking special (costly) measures to reduce the duration of an activity below its normal value |
Choose the correct answer from the options given below:
The following statements relate to project network. Choose the correct code for the statements being correct or incorrect.
Statement I: An activity cannot be represented by more than one arrow, but an arrow can represent one or more activities.
Statement II : The activities in a critical path can be preponed or postponed.
A public limited company has 9,00,000 shares outstanding at current market price of Rs. 130 per share. The company needs Rs. 2.25 crores to finance its proposed new project. The board of the company has decided to issue rights shares to raise the required money at Rs. 75 per share (as subscription price) to ensure that the rights issue is fully subscribed. How many rights are required to purchase a new share ?