A divide wall is provided-

The correct answer is

At right angle to the axis of weir

For effective separation and flow control, the divide wall is built at a right angle (perpendicular) to the axis of the weir or barrage. At right angle to the axis of weir - This placement aligns with the functional requirements of a divide wall, effectively separating flow to undersluices, preventing cross-currents, and aiding in silt management.