A contractor breaches a construction contract. The aggrieved party wishes to have the work completed by another contractor at the original contractor’s expense. Before doing so, the aggrieved party proposes to send a written notice giving the original contractor 20 days to perform. Which statement as per the Specific Relief Act, 1963, is correct ?
The statutory notice period is insufficient because Section 20 requires written notice of not less than thirty days before substituted performance.
Section 20 of the Specific Relief Act, 1963, inserted by the 2018 amendment, gives a party who suffers a breach of contract the option of substituted performance through a third party or his own agency, and to recover the expenses and costs from the party in breach.
Under Section 20(2), no substituted performance shall be undertaken unless the party who suffers the breach has given a notice in writing of not less than thirty days to the party in breach, calling upon him to perform the contract within the time specified, and the party in breach has refused or failed to do so.
A notice giving only twenty days falls short of the statutory minimum, so the aggrieved party must give at least thirty days before getting the work done by another contractor. The requirement is not waived merely because the breach is admitted.
Section 20(3) further provides that once the aggrieved party has got the contract performed through a third party, he is not entitled to claim relief of specific performance against the party in breach, so substituted performance does not give an added right of specific performance.
Hence, The statutory notice period is insufficient because Section 20 requires written notice of not less than thirty days before substituted performance.