All Exams Test series for 1 year @ ₹349 only
Question

A contract is to be completed in 52 days and 125 identical robots were employed, each operational for 7 hours a day. After 39 days, five-seventh of the work was completed. How many additional robots would be required to complete the work on time, if each robot is now operational for 8 hours a day?

The correct answer is

7

Contract Completion Problem Analysis

This problem involves understanding the relationship between the number of robots, their working hours, the number of days, and the amount of work completed. We will use the concept of "robot-hours" as a unit of work to solve this problem efficiently. The goal is to determine the additional robots required to complete the remaining work on time under new conditions.

Initial Work Phase Details

In the first phase of the contract, we have the following information:

  • Initial Robots (M1): 125 identical robots
  • Days Worked (D1): 39 days
  • Hours per Day (H1): 7 hours/day
  • Work Completed (W1): 5/7 of the total contract work

The total work completed in this phase can be calculated in "robot-hours":

\[ \text{Work Done} = M_1 \times D_1 \times H_1 \]

\[ \text{Work Done} = 125 \times 39 \times 7 \]

\[ \text{Work Done} = 34125 \text{ robot-hours} \]

This amount, 34125 robot-hours, represents 5/7 of the total work for the entire contract.

Calculating Total and Remaining Work

Since 34125 robot-hours represent 5/7 of the total work, we can find the total work required for the entire contract:

\[ \text{Total Work} = \text{Work Done} \times \frac{7}{5} \]

\[ \text{Total Work} = 34125 \times \frac{7}{5} \]

\[ \text{Total Work} = (34125 \div 5) \times 7 \]

\[ \text{Total Work} = 6825 \times 7 \]

\[ \text{Total Work} = 47775 \text{ robot-hours} \]

Now, we need to determine the remaining work that needs to be completed:

\[ \text{Remaining Work} = \text{Total Work} - \text{Work Done} \]

\[ \text{Remaining Work} = 47775 - 34125 \]

\[ \text{Remaining Work} = 13650 \text{ robot-hours} \]

Alternatively, the remaining work is \(1 - \frac{5}{7} = \frac{2}{7}\) of the total work:

\[ \text{Remaining Work} = \frac{2}{7} \times 47775 \]

\[ \text{Remaining Work} = 2 \times 6825 \]

\[ \text{Remaining Work} = 13650 \text{ robot-hours} \]

Remaining Time and New Work Conditions

The total contract duration is 52 days, and 39 days have already passed. So, the remaining time to complete the contract is:

  • Remaining Days (D2): \(52 - 39 = 13\) days

The new operational hours for each robot are:

  • New Hours per Day (H2): 8 hours/day

Calculating Robots Needed for Remaining Work

Let M2 be the total number of robots required to complete the remaining work (13650 robot-hours) within the remaining 13 days, with each robot working 8 hours/day.

\[ M_2 \times D_2 \times H_2 = \text{Remaining Work} \]

\[ M_2 \times 13 \times 8 = 13650 \]

\[ M_2 \times 104 = 13650 \]

To find M2, we divide the remaining work by the total robot-hours one robot can provide in the remaining time:

\[ M_2 = \frac{13650}{104} \]

\[ M_2 = 131.25 \text{ robots} \]

Determining Additional Robots Required

Since it is impossible to employ a fraction of a robot, and we need to ensure the work is completed on time, we must round up the number of robots to the next whole number. Therefore, 132 robots are required to complete the remaining work.

  • Total Robots Required (M2): 132 robots
  • Initial Robots Employed: 125 robots

The number of additional robots required is the difference between the total robots needed for the second phase and the robots already employed:

\[ \text{Additional Robots} = \text{Total Robots Required} - \text{Initial Robots Employed} \]

\[ \text{Additional Robots} = 132 - 125 \]

\[ \text{Additional Robots} = 7 \text{ robots} \]

Therefore, 7 additional robots are required to complete the work on time.

Was this answer helpful?

Important Questions from Numerical Computation

  1. Ratio of the angles of a triangle are 1 : 2 : 6. What is the smallest angle?

  2. It would take one machine 4 hours to complete a production order and another machine 2 hour to complete the same order. If both machines work simultaneously at their respective constant rates, the time taken to complete the same order is ________ hours.

  3. Two design consultants, P and Q, started working from 8 AM for a client. The client budgeted a total of USD 3000 for the consultants. P stopped working when the hour hand moved by 210 degrees on the clock. Q stopped working when the hour hand moved by 240 degrees. P took two tea breaks of 15 minutes each during her shift, but took no lunch break. Q took only one lunch break for 20 minutes, but no tea breaks. The market rate for consultants is USD 200 per hour and breaks are not paid. After paying the consultants, the client shall have USD_remaining in the budget.

  4. What is the value of \(1 + \frac{1}{4} + \frac{1}{{16}} + \frac{1}{{64}} + \frac{1}{{256}} + \ldots ?\)

  5. A 1.5 m tall person is standing at a distance of 3 m from a lamp post. The light from the lamp at the top of the post casts her shadow. The length of the shadow is twice her height. What is the height of the lamp post in meters?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App