A can complete a piece of work in 24 days and B can complete it in 28 days. If they work on alternate days, starting with B on the first day, then in how many days will the work be finished?
$25\frac{6}{7}$
This problem involves calculating the time taken to complete a task when two people, A and B, work on alternate days. We need to determine their individual work rates and how their combined effort progresses over the alternate days.
First, let's determine the amount of work each person completes in a single day.
They work on alternate days, with B starting first. This means a cycle of work consists of two days: Day 1 (B works) and Day 2 (A works).
To add these fractions, we find a common denominator. The least common multiple (LCM) of 28 and 24 is 168.
We need to find out how many such 2-day cycles are needed to complete the total work of 168 parts.
Divide the total work by the work done per cycle: $$ \frac{168 \text{ parts}}{13 \text{ parts/cycle}} = 12 \text{ cycles with a remainder} $$ Let's calculate the work done in exactly 12 cycles:
After 24 days, there is still some work left.
Wait, let's recheck the calculation.
After 12 cycles (24 days), 156 parts are done. Remaining work is 12 parts.
Day 25: B works. B completes 6 parts. Remaining work = $12 - 6 = 6$ parts.
Day 26: A works. A's rate is 7 parts per day. Time A needs for the remaining 6 parts = $\frac{6 \text{ parts}}{7 \text{ parts/day}} = \frac{6}{7}$ days.
The total time taken is the sum of the time for the full cycles and the time taken on the last day.
Therefore, the work will be finished in $25\frac{6}{7}$ days.
In a circular race on a track of length 2000 m, X and Y start from the same point at the same time in opposite directions at the speeds of 15 km/h and 33 km/h, respectively. After how much time will they meet next?
Which of the following option figures will complete the pattern in the figure given below?

A has completed two-third of a job in 8 days, and B completes the rest of the job in 20 days. In how many days can they together complete the job?
The smallest 4-digit prime number is:
If Anand can do a piece of work in 9 days and Vinod can complete the same work in 6 days, then in how many days will both of them complete it together?