All Exams Test series for 1 year @ ₹349 only
Question

A can complete a piece of work in 24 days and B can complete it in 28 days. If they work on alternate days, starting with B on the first day, then in how many days will the work be finished?

The correct answer is

$25\frac{6}{7}$

This problem involves calculating the time taken to complete a task when two people, A and B, work on alternate days. We need to determine their individual work rates and how their combined effort progresses over the alternate days.

Understanding Work Rates

First, let's determine the amount of work each person completes in a single day.

  • Person A can complete the work in 24 days. So, A's work rate is $\frac{1}{24}$ of the work per day.
  • Person B can complete the work in 28 days. So, B's work rate is $\frac{1}{28}$ of the work per day.

Calculating Work Done in Cycles

They work on alternate days, with B starting first. This means a cycle of work consists of two days: Day 1 (B works) and Day 2 (A works).

  1. Day 1 (B works): Work done = $\frac{1}{28}$
  2. Day 2 (A works): Work done = $\frac{1}{24}$
  3. Work done in 2 days (1 cycle): Sum of work done by B and A = $\frac{1}{28} + \frac{1}{24}$

To add these fractions, we find a common denominator. The least common multiple (LCM) of 28 and 24 is 168.

  • Work done by B in 2 days = $\frac{168}{28} = 6$ parts
  • Work done by A in 2 days = $\frac{168}{24} = 7$ parts
  • Total work done in 2 days = $6 + 7 = 13$ parts.
  • So, in every 2-day cycle, 13 parts of the total work (represented as 168 parts) are completed.

Determining the Number of Cycles

We need to find out how many such 2-day cycles are needed to complete the total work of 168 parts.

Divide the total work by the work done per cycle: $$ \frac{168 \text{ parts}}{13 \text{ parts/cycle}} = 12 \text{ cycles with a remainder} $$ Let's calculate the work done in exactly 12 cycles:

  • Number of days = $12 \text{ cycles} \times 2 \text{ days/cycle} = 24$ days.
  • Work completed in 24 days = $12 \text{ cycles} \times 13 \text{ parts/cycle} = 156$ parts.

Calculating Remaining Work and Time

After 24 days, there is still some work left.

  • Remaining work = Total work - Work done = $168 - 156 = 12$ parts.
  • The 24 days completed the 12th cycle, which ended with A working. The next day, Day 25, is B's turn.
  • B's work rate is 6 parts per day.
  • Time needed for B to complete the remaining 12 parts = $\frac{12 \text{ parts}}{6 \text{ parts/day}} = 2$ days.

Wait, let's recheck the calculation.

After 12 cycles (24 days), 156 parts are done. Remaining work is 12 parts.

Day 25: B works. B completes 6 parts. Remaining work = $12 - 6 = 6$ parts.

Day 26: A works. A's rate is 7 parts per day. Time A needs for the remaining 6 parts = $\frac{6 \text{ parts}}{7 \text{ parts/day}} = \frac{6}{7}$ days.

Total Time Calculation

The total time taken is the sum of the time for the full cycles and the time taken on the last day.

  • Time for 12 cycles = 24 days.
  • Time for the remaining work = 1 day (B on Day 25) + $\frac{6}{7}$ days (A on Day 26) = $1\frac{6}{7}$ days.
  • Total time = $24 + 1\frac{6}{7} = 25\frac{6}{7}$ days.

Therefore, the work will be finished in $25\frac{6}{7}$ days.

Was this answer helpful?

Important Questions from Time and work

  1. 5 men can complete a piece of work in 18 days, while 9 women can do it in 5 days. In how many days can 3 women and 3 men complete this work?
  2. A can lay railway track between two given stations in 16 days and B can do the same job in 11 days. With the help of C, they did the job in 3 days only. Then, C alone can do the job in
  3. A can lay railway track between two given stations in 17 days and B can do the same job in 16 days. With the help of C, they did the job in 4 days only. Then, C alone can do the job in __________

  4. A can do a work in 10 days and B can do the same work in 20 days. If they work on it together for 6 days, then what fraction of the work is left?
  5. Jaya can do a certain piece of work in 30 days. Jaya and Sushma can together do the same work in 21 days, and Jaya, Sushma and Hina can do the same work together in 14 days. In how many days can Jaya and Hina do the same work together?
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App