A can complete a piece of work in 24 days and B can complete it in 28 days. If they work on alternate days, starting with B on the first day, then in how many days will the work be finished?
$25\frac{6}{7}$
This problem involves calculating the time taken to complete a task when two people, A and B, work on alternate days. We need to determine their individual work rates and how their combined effort progresses over the alternate days.
First, let's determine the amount of work each person completes in a single day.
They work on alternate days, with B starting first. This means a cycle of work consists of two days: Day 1 (B works) and Day 2 (A works).
To add these fractions, we find a common denominator. The least common multiple (LCM) of 28 and 24 is 168.
We need to find out how many such 2-day cycles are needed to complete the total work of 168 parts.
Divide the total work by the work done per cycle: $$ \frac{168 \text{ parts}}{13 \text{ parts/cycle}} = 12 \text{ cycles with a remainder} $$ Let's calculate the work done in exactly 12 cycles:
After 24 days, there is still some work left.
Wait, let's recheck the calculation.
After 12 cycles (24 days), 156 parts are done. Remaining work is 12 parts.
Day 25: B works. B completes 6 parts. Remaining work = $12 - 6 = 6$ parts.
Day 26: A works. A's rate is 7 parts per day. Time A needs for the remaining 6 parts = $\frac{6 \text{ parts}}{7 \text{ parts/day}} = \frac{6}{7}$ days.
The total time taken is the sum of the time for the full cycles and the time taken on the last day.
Therefore, the work will be finished in $25\frac{6}{7}$ days.
A person can complete 20% of work in 8 days and another person y can complete 25% of the same work in 6 days. If they work together, in how many days will 40% of the work be completed?
P works thrice as fast as Q, whereas P and Q together can work four times as fast as R. If P, Q and R together work on a job, in what ratio should they share the earnings?
There are three pillars X, Y and Z of different heights. Three spiders A, B and C start to climb on these pillars simultaneously. In one chance, A climbs on X by 6 cm but slips down 1 cm. B climbs on Y by 7 cm but slips down 3 cm. C climbs on Z by 6.5 cm but slips down 2 cm. If each of them requires 40 chances to reach the top of the pillars, what is the height of the shortest pillar?
There is an order of 19000 quantity of a particular product from a customer. The firm produces 1000 quantity of that product per out of which 5% are unfit for sale. In how many days will the order be completed?
Ram and Shyam work on a job together for four days and complete 60% of it. Ram takes leave then and Shyam works for eight more days to complete the job. How long would Ram take to complete the entire job alone?