All Exams Test series for 1 year @ ₹349 only
Question

A, B and C together can complete a certain work in 54 days. B and C together can complete the same work in 56 days. B is 75% more efficient than A. A, B and C work together for 52 days. B alone will complete the remaining work in:

The correct answer is
32 days

Solving Work Efficiency Problem for A, B, and C

1. Calculate Individual Work Rates

Let the total amount of work be represented by units. We find the least common multiple (LCM) of the days given for combined work to establish a common unit base.

LCM of 54 and 56 is 1512 units. This is the total work.

  • Rate of A, B, and C working together:

    $ \text{Rate}_{(A+B+C)} = \frac{1512 \text{ units}}{54 \text{ days}} = 28 \text{ units/day} $

  • Rate of B and C working together:

    $ \text{Rate}_{(B+C)} = \frac{1512 \text{ units}}{56 \text{ days}} = 27 \text{ units/day} $

  • Calculate Rate of A:

    $ \text{Rate}_{(A)} = \text{Rate}_{(A+B+C)} - \text{Rate}_{(B+C)} = 28 - 27 = 1 \text{ unit/day} $

2. Determine B's Work Rate using Efficiency

B is 75% more efficient than A. This means B's rate is A's rate plus 75% of A's rate.

  • Efficiency calculation:

    $ \text{Rate}_{(B)} = \text{Rate}_{(A)} \times (1 + 0.75) = \text{Rate}_{(A)} \times 1.75 = \text{Rate}_{(A)} \times \frac{7}{4} $

  • Substitute Rate of A:

    $ \text{Rate}_{(B)} = 1 \text{ unit/day} \times \frac{7}{4} = \frac{7}{4} \text{ units/day} $

3. Calculate Work Done and Remaining Work

A, B, and C work together for 52 days. Calculate the work completed during this period.

  • Work done in 52 days:

    $ \text{Work done} = \text{Rate}_{(A+B+C)} \times \text{Days} = 28 \text{ units/day} \times 52 \text{ days} = 1456 \text{ units} $

  • Calculate remaining work:

    $ \text{Remaining Work} = \text{Total Work} - \text{Work done} = 1512 \text{ units} - 1456 \text{ units} = 56 \text{ units} $

4. Calculate Time for B to Complete Remaining Work

Find how many days B will take to complete the remaining 56 units of work, using B's calculated work rate.

  • Time calculation:

    $ \text{Days for B} = \frac{\text{Remaining Work}}{\text{Rate}_{(B)}} = \frac{56 \text{ units}}{\frac{7}{4} \text{ units/day}} $

    $ \text{Days for B} = 56 \times \frac{4}{7} = 8 \times 4 = 32 \text{ days} $

B alone will complete the remaining work in 32 days.

Was this answer helpful?

Important Questions from Time and work

  1. 5 men can complete a piece of work in 18 days, while 9 women can do it in 5 days. In how many days can 3 women and 3 men complete this work?
  2. A can lay railway track between two given stations in 16 days and B can do the same job in 11 days. With the help of C, they did the job in 3 days only. Then, C alone can do the job in
  3. A can lay railway track between two given stations in 17 days and B can do the same job in 16 days. With the help of C, they did the job in 4 days only. Then, C alone can do the job in __________

  4. A can do a work in 10 days and B can do the same work in 20 days. If they work on it together for 6 days, then what fraction of the work is left?
  5. Jaya can do a certain piece of work in 30 days. Jaya and Sushma can together do the same work in 21 days, and Jaya, Sushma and Hina can do the same work together in 14 days. In how many days can Jaya and Hina do the same work together?
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App