A, B, and C alone can do a piece of work in 9, 12, and 18 days, respectively. They all started the work together, but A left after 3 days. In how many days, was the total work completed?
24/5
The work done by A, B, and C in one day is:
A's rate = 1/9, B's rate = 1/12, C's rate = 1/18.
The total work done by all three in one day is:
1/9 + 1/12 + 1/18 = 4/36 + 3/36 + 2/36 = 9/36 = 1/4 (Total work per day).
After 3 days, the work done is: 3 * 1/4 = 3/4.
The remaining work = 1 - 3/4 = 1/4.
After A leaves, B and C work together. Their combined rate is:
B + C's rate = 1/12 + 1/18 = 5/36.
The time taken by B and C to complete the remaining work = (1/4) ÷ (5/36) = 36/20 = 9/5 days.
Therefore, the total time taken to complete the work is 3 days (when all worked) + 9/5 days (after A left), which is 24/5 days.
The magazine in which Mahatma Gandhi mentioned what he wanted the Constitution to do is:
Which gas shields the surface of the earth from ultraviolet radiation from the sun?
Which event is marked as an Intangible Cultural Heritage of Humanity by UNESCO?
Who has been conferred with the rank of the Commander of the Order of the British Empire in 2018?
Who directead the film ‘Bhuvan Shome’?