All Exams Test series for 1 year @ ₹349 only
Question

A and B complete a work in 21 days. If A alone can do it in 28 days, then B alone can do three-fourth of the same work in ______________days.

The correct answer is
63

Work and Time: Finding B's Time for 3/4 Work

We are given that A and B together can complete a piece of work in 21 days. A alone can complete the same work in 28 days. We need to find the time B takes to complete three-fourth ($ \frac{3}{4} $) of the work.

Calculating Individual Work Rates

  • Let the total work be represented by 1 unit.
  • Combined work rate of A and B = $ \frac{1 \text{ work}}{21 \text{ days}} $.
  • A's work rate = $ \frac{1 \text{ work}}{28 \text{ days}} $.

Determining B's Work Rate

To find B's individual work rate, we subtract A's rate from the combined rate:

B's work rate = (A and B's combined rate) - (A's rate)

B's work rate = $ \frac{1}{21} - \frac{1}{28} $ work per day.

To subtract these fractions, we find the least common multiple (LCM) of 21 and 28, which is 84.

B's work rate = $ \frac{4}{84} - \frac{3}{84} = \frac{1}{84} $ work per day.

Calculating Time for B to Complete 3/4 Work

This means B completes $ \frac{1}{84} $ of the work each day. Therefore, B takes 84 days to complete the entire work.

We need to find the time B takes to complete only three-fourth ($ \frac{3}{4} $) of the work.

Time for B to do $ \frac{3}{4} $ work = $ \frac{3}{4} \times (\text{Time for B to do full work}) $

Time = $ \frac{3}{4} \times 84 $ days

Time = $ 3 \times \frac{84}{4} $ days

Time = $ 3 \times 21 $ days

Time = 63 days.

Thus, B alone can do three-fourth of the same work in 63 days.

Was this answer helpful?

Important Questions from Time and work

  1. In a circular race on a track of length 2000 m, X and Y start from the same point at the same time in opposite directions at the speeds of 15 km/h and 33 km/h, respectively. After how much time will they meet next?

  2. Which of the following option figures will complete the pattern in the figure given below?

  3. A has completed two-third of a job in 8 days, and B completes the rest of the job in 20 days. In how many days can they together complete the job?

  4. The smallest 4-digit prime number is:

  5. If Anand can do a piece of work in 9 days and Vinod can complete the same work in 6 days, then in how many days will both of them complete it together?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App