All Exams Test series for 1 year @ ₹349 only
Question

100 men have provisions for 26 days. If 60 men have left, for how many days the same provisions would last for the remaining men?

The correct answer is
65

This problem involves calculating the duration for which provisions will last based on the number of men. It demonstrates an inverse proportion relationship: as the number of men decreases, the number of days the provisions last increases.

Understanding Provisions Calculation

We are given:

  • Initial number of men ($M_1$) = 100
  • Number of days provisions last initially ($D_1$) = 26
  • Number of men who left = 60

Calculating Remaining Men

First, determine the number of men remaining:

Remaining men ($M_2$) = Initial men - Men who left

$M_2 = 100 - 60 = 40$ men

Calculating Duration for Remaining Men

The total amount of provisions can be thought of in terms of "man-days". The relationship between the number of men and the number of days the provisions last is inversely proportional. This can be represented by the formula:

$M_1 \times D_1 = M_2 \times D_2$

Where:

  • $M_1$ = Initial number of men
  • $D_1$ = Initial number of days
  • $M_2$ = Remaining number of men
  • $D_2$ = Number of days the provisions will last for the remaining men

Substitute the known values into the formula:

$100 \times 26 = 40 \times D_2$

Calculate the total man-days:

$2600 = 40 \times D_2$

Now, solve for $D_2$:

$D_2 = \frac{2600}{40}$

$D_2 = \frac{260}{4}$

$D_2 = 65$

Therefore, the same provisions would last for 65 days for the remaining 40 men.

Was this answer helpful?

Important Questions from Time and work

  1. In a circular race on a track of length 2000 m, X and Y start from the same point at the same time in opposite directions at the speeds of 15 km/h and 33 km/h, respectively. After how much time will they meet next?

  2. Which of the following option figures will complete the pattern in the figure given below?

  3. A has completed two-third of a job in 8 days, and B completes the rest of the job in 20 days. In how many days can they together complete the job?

  4. The smallest 4-digit prime number is:

  5. If Anand can do a piece of work in 9 days and Vinod can complete the same work in 6 days, then in how many days will both of them complete it together?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App